test/TestSuite/Syntax/Correct/Complete.tjp in taskjuggler-3.0.0 vs test/TestSuite/Syntax/Correct/Complete.tjp in taskjuggler-3.1.0
- old
+ new
@@ -1,17 +1,20 @@
-project simple "Simple Project" "1.0" 2007-01-01 - 2007-01-30 {
+project simple "Simple Project" "1.0" 2007-01-01 +2m {
timezone "America/Denver"
now 2007-01-15
}
# *** EXAMPLE: 1 +
-resource tux "Tux"
-task t "Task" {
+task "Build house" {
start 2007-01-06
- effort 10d
- allocate tux
+ duration 30d
# This task should have been completed on Jan 15, but only
# 20% of the task have been completed so far.
complete 20
+}
+
+taskreport "Complete" {
+ formats html
+ columns name, end { title "Due date" }, complete, gauge, chart
}