test/TestSuite/Scheduler/Correct/Shift2.tjp in taskjuggler-3.0.0 vs test/TestSuite/Scheduler/Correct/Shift2.tjp in taskjuggler-3.1.0
- old
+ new
@@ -1,11 +1,11 @@
project "Shift2" 2010-02-06 +1w
include "checks.tji"
shift s2 "s2" {
- replace
+ replace
workinghours mon - fri 8:00 - 16:00
}
shift s3 "s3" {
vacation 2010-02-09
@@ -27,30 +27,30 @@
allocate r1
${FixEnd "2010-02-12-17:00"}
}
resource r2 "r2" {
- shift s2 2010-02-08 +1w
+ shifts s2 2010-02-08 +1w
}
task "T2" {
effort 40h
allocate r2
${FixEnd "2010-02-12-16:00"}
}
resource r3 "r3" {
- shift s3 2010-02-08 +1w
+ shifts s3 2010-02-08 +1w
}
task "T3" {
effort 24h
allocate r3
${FixEnd "2010-02-12-16:00"}
}
resource r4 "r4" {
- shift s4 2010-02-08 +1w
+ shifts s4 2010-02-08 +1w
}
task "T4" {
effort 32h
allocate r4