test/TestSuite/Scheduler/Correct/Depends.tjp in taskjuggler-3.5.0 vs test/TestSuite/Scheduler/Correct/Depends.tjp in taskjuggler-3.6.0
- old
+ new
@@ -1,9 +1,12 @@
project test "Test" "1.0" 2007-04-02 +3m
include "checks.tji"
+resource r1 "R1"
+resource r2 "R2"
+
task t1 "T1" {
start ${projectstart}
duration 1w
${FixEnd "2007-04-09"}
}
@@ -34,9 +37,23 @@
task t6 "T6" {
depends t4 { onstart gaplength 1w }
duration 1w
${FixTask "2007-05-11-17:00" "2007-05-18-17:00"}
+}
+
+task t7 "T7" {
+ start ${projectstart}
+ effort 1w
+ allocate r1
+ ${FixEnd "2007-04-06-17:00"}
+}
+
+task t8 "T8" {
+ depends t7 { onstart gaplength 1w }
+ effort 1w
+ allocate r2
+ ${FixTask "2007-04-9-9:00" "2007-04-13-17:00"}
}
taskreport depends "Depends" {
formats html
columns name, start, end, daily