project "Priority Demo" 2011-04-17-0:00--0700 +2m { timezone "America/Denver" } resource tux "Tux" # *** EXAMPLE: project + task jobs "Project breakdown" { start ${projectstart} task work "The regular work" { effort 20d priority 500 allocate tux limits { weeklymax 25h } } task support "Customer Support" { # This is a high priority task. Due to the high priority tux is # spending the required daily maximum on it. end ${projectend} priority 800 allocate tux limits { dailymax 2h } } task conference "Attend Conference" { period 2011-04-25 +2d allocate tux priority 1000 } task maintenance "Maintenance work" { # This is a fallback task. Whenever tux is not doing something # else he is allocated to this task. end ${projectend} priority 300 allocate tux limits { weeklymax 2d } } } # *** EXAMPLE: project -