project test "Test" "1.0" 2007-04-02 +3m include "checks.tji" task t1 "T1" { start ${projectstart} duration 1w ${FixEnd "2007-04-09"} } task t2 "T2" { depends t1 duration 1w ${FixTask "2007-04-09" "2007-04-16"} } task t3 "T3" { depends t2 { gapduration 1w } duration 1w ${FixTask "2007-04-23" "2007-04-30"} } task t4 "T4" { depends t3 { onend gaplength 1w } duration 1w ${FixTask "2007-05-04-18:00" "2007-05-11-18:00"} } task t5 "T5" { depends t4 { onstart } duration 1w ${FixTask "2007-05-04-18:00" "2007-05-11-18:00"} } task t6 "T6" { depends t4 { onstart gaplength 1w } duration 1w ${FixTask "2007-05-11-18:00" "2007-05-18-18:00"} } taskreport depends "Depends" { formats html columns name, start, end, daily }