Road and bridge projects are expected to make up one of the biggest chunks of the jobs created in the stimulus package. Below, you’ll find a chart of more than 5,800 projects that have been approved by the U.S. Department of Transportation. Once given the green light, states can put the projects out to bid, contract them and begin construction work. So far, about 2,300 projects are under way.
Help us find out how much progress has been made on these projects by participating in our Stimulus Spot Check.
For more on the stimulus, check out our blog and resource page.
State | Urban Area | Project Description | Improvement Type | ARRA Funds Obligated |
---|---|---|---|---|
ALABAMA | HUNTSVILLE | SR-1 (MEMORIAL PKY) FR CR-85 (OAKWOOD AV) TO CR-22 (SPARKMAN DR) INCLUDING AN OVERPASS AT CR-22 (PRIORITY #9-2008) | Pavement Improvement | $25,534,292 |
ALABAMA | DOTHAN | RETROFIT BRIDGE RAILS ON SR-1 (US-231) AT BIN 006900 AND 006901 @ BIG CREEK | Pavement Improvement | $154,446 |
ALABAMA | DOTHAN | RESURFACE SR-1 (US-231) FROM FLORIDA STATE LINE TO END OF PAVED SHOULDERS NORTH OF CR-93 | Pavement Improvement | $2,850,120 |
ALABAMA | RESURFACE SR-1 (US-431) FROM HEADLAND SOUTH CITY LIMIT TO NORTH OF SR-173 | Pavement Improvement | $2,209,099 | |
ALABAMA | COLUMBUS (GA) | RESURFACE SR-1 (US-431) FROM CR-137 (OLD SEALE HWY) TO 0.6 MILE SOUTH SR-38 (US-280), FY 2009 PHASE 2, | Pavement Improvement | $5,821,097 |
ALABAMA | WIDENING & RESURFACING SR-1 (US-431) FROM NORTH END OF THE TENN. RIVER BRIDGE TO CR-5 (CATHEDRAL CAVERNS HWY) | Pavement Improvement | $3,761,469 | |
ALABAMA | FLORENCE | RESURFACE & 2 FT. PAVEMENT WIDENING SR-2 (US-72) FROM 0.6 MILE WEST CANE CREEK TO 0.449 MILE EAST OF DRY | Pavement Improvement | $1,659,388 |
ALABAMA | RESURFACING AND PAVEMENT WIDENING SR-3 (US-31) FROM JUST SOUTH OF CACTUS STREET TO I-65 NEAR CITY OF ATHENS | Pavement Improvement | $1,220,429 | |
ALABAMA | RESURFACING SR-3 (US-31) FROM 0.24 MILE NORTH OF SR-59 INTERSECTION IN STAPLETON TO BAY MINETTE SOUTH CITY LIMITS | Pavement Improvement | $2,886,968 | |
ALABAMA | RESURFACE & 2' WIDENING ON SR-3 (US-31) FROM CONECUH COUNTY LINE TO 0.8 MILE NORTH PERSIMMON CREEK (FY2009 PHASE2) | Pavement Improvement | $2,335,367 | |
ALABAMA | RESURFACE & 2' WIDENING ON SR-3 (US-31) FROM JUNCTION OF SR-185 TO MONTGOMERY COUNTY LINE (FY2009 PHASE2) | Pavement Improvement | $4,383,448 | |
ALABAMA | RESURFACING SR-3 (US-31) FROM SR-12 (US-84) TO BUTLER COUNTY LINE. FY 2009 PHASE 2 | Pavement Improvement | $2,453,411 | |
ALABAMA | PLANING RESURFACE AND TRAFFIC STRIPE SR-5 FROM SR-13(US-43) TO WILCOX COUNTY LINE 2009 PHASE 1 | Pavement Improvement | $1,619,174 | |
ALABAMA | MONTGOMERY | RESURFACE & 2' WIDENING ON SR-6 (US-82) FROM JUST WEST OF CR-40 TO SR-206 | Pavement Improvement | $4,938,746 |
ALABAMA | TUSCALOOSA | RESURFACE SR-7 (US-11) FROM GREENE COUNTY LINE TO JUST SOUTH OF WARRIOR RIVER BRIDGE AT FOSTERS AND HOLLY SPRINGS ROAD FROM SR-7 (US-11) TO JUST SOUTH OF THE I-20/59 INTERCHANGE | Pavement Improvement | $4,415,517 |
ALABAMA | PLANING, PAVEMENT WIDENING AND RESURFACING SR-7 (US-11) FROM NORTH OF CR-208 (GREENETRACK RD.) TO TUSCALOOSA COUNTY LINE. FY2009 PHASE 2 | Pavement Improvement | $3,357,073 | |
ALABAMA | RESURFACE & 2' WIDENING ON SR-8 (US-80) FROM NEAR JUNCTION OF SR-186 TO LEE COUNTY LINE (FY2010 PHASE1) | Pavement Improvement | $3,198,619 | |
ALABAMA | RESURFACING AND TRAFFIC STRIPE ON SR-10 FROM SR-28 TO SR-41, FY2009 PHASE 2; | Pavement Improvement | $720,697 | |
ALABAMA | RESURFACING AND PAVEMENT WIDENING ON SR-10 FROM BUTLER COUNTY LINE TO SR-9 (US-331). FY2010 PHASE 1 | Pavement Improvement | $2,981,219 | |
ALABAMA | RESURFACE ON SR-15 (US-29) FROM SR-197 TO SR-6 (US-82) (FY2009 PHASE II) | Pavement Improvement | $512,187 | |
ALABAMA | AUBURN-OPELIKA | RESURFACING SR-15 (US-29) FROM MACON COUNTY TO SOUTH CR-010 (SAND HILL RD), FY2009 PHASE 2 | Pavement Improvement | $908,101 |
ALABAMA | WIDENING, RESURFACING & TRAFFIC STRIPE SR-17 FROM 1.3 MILES SOUTH CR-18 TO 0.7 MILES NORTH OF CR-28 | Pavement Improvement | $1,321,334 | |
ALABAMA | RESURFACING & TRAFFIC STRIPE ON SR-17 FROM 0.7 MI NORTH OF CR-28 TO NORTH OF SOUTH BUTLER CITY LIMITS | Pavement Improvement | $1,257,489 | |
ALABAMA | PLANE/RESURFACE SR-17 FROM 0.7 MILE NORTH CR-29 TO CR-30 IN SULLIGENT, FY2009 PHASE 2 | Pavement Improvement | $6,084,240 | |
ALABAMA | RESURFACING AND STRIPING SR-17 FROM LAMAR COUNTY LINE TO SR-4 | Pavement Improvement | $1,770,060 | |
ALABAMA | FY 2010 PHASE 1, PLANING AND RESURFACING ON SR-17 FROM SR-28 TO CR-24 | Pavement Improvement | $2,709,873 | |
ALABAMA | FY 2010 PHASE 1, PLANING AND RESURFACING ON SR-17 FROM 1.7 MILES SOUTH OF CR-20 TO SR 56, IN CHATOM | Pavement Improvement | $3,517,300 | |
ALABAMA | RESURFACE SR17 FROM SOUTH CITY LMITIES OF CARROLTON TO 0.6 MILE NORTH CARROLLTON NORTH CITY LIMITS IN PICKENS CO | Pavement Improvement | $1,944,144 | |
ALABAMA | RESURFACE SR-20 FROM THE TENNESSEE STATE LINE TO SOUTH OF CR-22 AT THE NATCHEZ TRACE PARKWAY; PHASE II RESURFACING BUDGET | Pavement Improvement | $2,195,023 | |
ALABAMA | RESURFACING AND TRAFFIC STRIPE ON SR-21 FROM NORTH END OF LITTLE RIVER BRIDGE @ COUNTY LINE TO NORTH OF CR-8, FY2009 PHASE 2; | Pavement Improvement | $2,344,547 | |
ALABAMA | RESURFACE AND TRAFFIC STRIPE ON SR-21 FROM NORTH OF CR-8 TO SOUTH OF CR-10, FY2009 PHASE 2; | Pavement Improvement | $2,264,245 | |
ALABAMA | RESURFACING SR-21 FROM THE FLORIDA STATE LINE TO MP 0.968, FY 2009 PHASE 2 | Pavement Improvement | $368,368 | |
ALABAMA | RESURFACE SR-21 FROM CR-947 (MAXWELLBORN RD) TO NEAR FOOTHILLS DR, FY 2009 PHASE 2 | Pavement Improvement | $1,898,929 | |
ALABAMA | RESURFACE & 2' WIDENING ON SR-22 FROM SR-5 TO SR-219 (FY2010 PHASE1) | Pavement Improvement | $5,225,138 | |
ALABAMA | RESURFACE SR-24 FROM CR-460 TO NEAR CR-320. FY 2009 PHASE II RESURFACING BUDGET | Pavement Improvement | $3,792,260 | |
ALABAMA | PLANING, PAVEMENT WIDENING AND RESURFACING SR-25 FROM CR-29 TO BIBB COUNTY LINE, FY2009 PHASE 2 | Pavement Improvement | $1,905,541 | |
ALABAMA | RESURFACING AND PAVEMENT WIDENING ON SR-27 FROM INDEGO PL TO DALE COUNTY LINE (FY2009 PHASE 2) | Pavement Improvement | $1,718,249 | |
ALABAMA | RESURFACE SR-33 FROM SR-74 TO NORTH END OF SIPSEY RIVER BRIDGE | Pavement Improvement | $2,021,675 | |
ALABAMA | 2' PAVEMENT WIDENING & RESURFACING SR-35 FROM SR-79 INTERSECTION WESTERLY THROUGH WOODVILLE TO THE JUNCTION OF SR-2 (US-72) | Pavement Improvement | $1,376,799 | |
ALABAMA | DECATUR | 2' PAVEMENT WIDENING AND RESURFACING SR-36 FROM INTERSECTION WITH US-31 (SR-3) IN HARTSELLE AT MP 21.15 TO I-65 INTERCHANGE AT MP 23.55. FY 2010 PHASE 1 RESURFACING PROGRAM | Pavement Improvement | $974,234 |
ALABAMA | BIRMINGHAM | RESURFACE SR-38 (US-280) FROM CR-353 (HUGH DANIEL DR) TO CR-280 (OLD US 280) | Pavement Improvement | $6,551,704 |
ALABAMA | RESURFACE SR-49 FROM TALLAPOOSA COUNTY LINE TO SR-77, FY 2009 PHASE 2 | Pavement Improvement | $2,355,118 | |
ALABAMA | RESURFACING AND PAVEMENT WIDENING ON SR-51 FROM JUST SOUTH OF SR-239 TO THE BULLOCK COUNTY LINE (FY2009 PHASE 2) | Pavement Improvement | $2,852,842 | |
ALABAMA | RETROFIT BRIDGE RAILS ON SR-53 (US-231) AT BIN 005532, 005533 (LITTLE CLAYBANK CREEK) & 005571, 009388 (BEAR CREEK) | Bridge Improvement | $102,730 | |
ALABAMA | RESURFACE SR-53 (US-231) FROM 0.2 MILE SOUTH OF SR-27 TO 0.06 MILE NORTH OF CR-2 | Pavement Improvement | $2,768,226 | |
ALABAMA | RESURFACING SR-53 (US-231) FROM NORTH OF I-20 TO 2.7 MILES NORTH OF WATTSVILLE | Pavement Improvement | $1,824,034 | |
ALABAMA | RESURFACE SR-55 FROM SR-12 (US-84) TO NORTH CITY LIMITS OF RED LEVEL (FY 2009 PHASE 2) | Pavement Improvement | $2,290,656 | |
ALABAMA | RESURFACE SR-55 FROM CONECUH COUNTY LINE TO SR-3 (US-31) (FY2009 PHASE2) | Pavement Improvement | $579,840 | |
ALABAMA | WIDEN SR-69 FROM SR-13 (US-43) TO HALE COUNTY LINE | Pavement Improvement | $1,012,013 | |
ALABAMA | RESURFACING SR-69 FROM I-65 IN GOOD HOPE TO SR-3 (US-31) IN CULLMAN | Pavement Improvement | $1,614,641 | |
ALABAMA | 2 FT. SAFETY WIDENING, RESURFACE, AND CULVERT EXTENSION ON SR-69 FROM MARENGO/HALE COUNTY LINE TO SR-8 (US-80), FY2009 PHASE 2 | Pavement Improvement | $570,127 | |
ALABAMA | RESURFACE & TRAFFIC STRIPE SR-69 FROM SR-13 (US-43) TO HALE COUNTY LINE | Pavement Improvement | $3,424,090 | |
ALABAMA | RESURFACE, STRIPING SR-75 FROM CR-363 (BROOKS LANE) IN ALLGOOD TO CR-58 (2ND ST) IN ONEONTA | Pavement Improvement | $1,783,600 | |
ALABAMA | BIRMINGHAM | PLANING, RESURFACING SR-79 FROM WINEWOOD ROAD TO SR-151 | Pavement Improvement | $2,606,952 |
ALABAMA | RESURFACE SR-93 FROM SR-53 (US-231) TO THE NORTH CITY LIMITS OF BRUNDIDGE (FY 2009 PHASE 2) (CSX RR) | Pavement Improvement | $772,677 | |
ALABAMA | MONTGOMERY | RESURFACE & 2' WIDENING ON SR-97 FROM CRENSHAW COUNTY LINE TO NORTH OF JUNCTION OF SR-3 (US-31) (FY2009 PHASE2) | Pavement Improvement | $729,364 |
ALABAMA | RESURFACING AND PAVEMENT WIDENING ON SR-103 FROM THE FLORIDA STATE LINE TO SR-52 IN SLOCOMB (FY 2009 PHASE 2) | Pavement Improvement | $2,606,280 | |
ALABAMA | RESURFACE SR-115 FROM SR-9 TO SR-38 (US-280), FY 2009 PHASE 2 | Pavement Improvement | $1,299,848 | |
ALABAMA | RESURFACE SR-118 FROM 4TH STREET IN CARBON HILL TO CR-298 (RIPLEY LOOP ROAD) | Pavement Improvement | $1,478,787 | |
ALABAMA | RESURFACE SR-129 FROM SR-171 (US-43) TO CR-49 IN HUBBERTVILLE, 2009 PHASE II | Pavement Improvement | $1,577,067 | |
ALABAMA | RESURFACE SR-139 FROM SIX MILE CREEK TO 0.100 MILE NORTH OF SHELBY COUNTY LINE, FY2010 PHASE I | Pavement Improvement | $2,791,631 | |
ALABAMA | RESURFACING, SR 148, 2'WIDENING AND STRIPING FROM SR 21 TO EAST CITY LIMITS OF SYLACAUGA | Pavement Improvement | $709,237 | |
ALABAMA | PLANING, PAVEMENT WIDENING AND RESURFACING SR-155 FROM NEAR CR-33 TO SHELBY COUNTY LINE . FY2009 PHASE 2 | Pavement Improvement | $2,007,167 | |
ALABAMA | FLORENCE | RESURFACING, STRIPING, AND BRIDGE RAIL RETROFIT SR 157 FROM LAWRENCE COUNTY LINE TO SR 20. FY 2009 ECONOMIC STIMULUS PROJECT. | Pavement Improvement | $4,097,292 |
ALABAMA | PLANING, PAVEMENT WIDENING AND RESURFACING SR-175 FROM SR-14 NEAR HEIBERGER TO SR-5, FY2009 PHASE 2 | Pavement Improvement | $2,142,465 | |
ALABAMA | ANNISTON | ANNISTON E. BYPASS FROM 1500' SOUTH OF LAKE YAHOU TO SR-1 (US-431) ; GRADE DRAIN BRIDGE PARTIAL BASE AND PAVE | New Construction | $46,770,227 |
ALABAMA | MOBILE | PAVEMENT WIDENING & RESURFACING ON SR-213 FROM SR-158 TO SR-13 (US-43) | Pavement Improvement | $691,974 |
ALABAMA | RESURFACE & 2' WIDENING ON SR223 FROM BULLOCK CO HIGH SCHOOL TO JUNCTION OF SR 6 (US82) FY2009 PHASE 2 | Pavement Improvement | $486,931 | |
ALABAMA | RESURFACING AND STRIPING SR 241 FROM JUST SOUTH OF THE MARION COUNTY LINE TO SR 237 | Pavement Improvement | $319,306 | |
ALABAMA | WIDENING & RESURFACING SR-273 FROM SR-68 IN LEESBURG TO AL-35 NEAR BLANCHE. FY 2009 PHASE 2 RESURFACING PROGRAM | Pavement Improvement | $5,743,428 | |
ALABAMA | FULL DEPTH RECLAMATION CR-267 FROM CR-222 IN FREDONIA TO SR-1 (US-431) SOUTH OF STROUD - CCP 09-09-01 | Pavement Improvement | $265,000 | |
ALABAMA | FLORENCE | RESURFACING CR-57 FROM CR-61 TO SR-20 CCP 17-200-08 | Pavement Improvement | $382,520 |
ALABAMA | RESURFACE CR-709 FROM SR-167 TO SR-134 CCP 16-05-07 | Pavement Improvement | $265,000 | |
ALABAMA | WIDEN & RESURFACE CR-99 FROM CR-41 TO CR-107 HCP 34-93-07 | Pavement Improvement | $265,000 | |
ALABAMA | BIN 003313 - BR ON CR-438 (E COOK RD.) @ CEDAR CREEK APPROX. 0.5 MILES NORTH OF ED TOLAR RD. (AASHTO) HCP 35-119-99 | Bridge Replacement | $265,000 | |
ALABAMA | DECATUR | RESURFACE SOUTH SENECA DRIVE FROM TRINITY TOWN LIMITS TO DEANNA BRIDGE HIGHWAY (STATE SUPPORT SERVICES) | Other | $3,827 |
ALABAMA | RESURFACING CR-2276 FROM CRENSHAW CO. LINE TO CR-2290 AND CR-2290 FROM CR-2276 TO CR-2262 IN HENDERSON PCP 55-98-07 | Pavement Improvement | $265,000 | |
ALABAMA | WIDEN & RESURFACE CR-82 FROM THE MEADOWS BRIDGE (LITTLE TALLAPOOSA RIVER) TO CR-87 - RCP 56-219-07 | Pavement Improvement | $265,000 | |
ALABAMA | BIRMINGHAM | CR-97 (SHADES CREST RD) INTERSECTION IMPROVEMENT @ CR-42 (WEST OXMOOR RD) & TYLER RD, PH VII PROJECT SPONSOR CITY OF HOOVER | Pavement Improvement | $2,201,171 |
ALABAMA | ANNISTON | RESURFACE CR187 (FRIENDSHIP RD) FROM CR193 (BOILING SPRING RD) TO SR21 | Other | $67,600 |
ALABAMA | MOBILE | RESURFACE CR656 (SPRINGHILL AVE) FROM MCGREGOR AVE TO I65) | Pavement Improvement | $287,500 |
ALABAMA | MOBILE | RESURFACE CR656 (SPRINGHILL AVE) FROM I65 TO SR42 (US98 MOFFETT RD) | Pavement Improvement | $165,499 |
ALABAMA | MOBILE | RESURFACE WEST MAIN ST FROM PRICHARD AVE TO BRANCH AVE | Other | $75,887 |
ALABAMA | MOBILE | WIDEN & OVERLAY EXISTING LANES ON VIADUCT RD FROM EAST ON MIKE BOX BR TO WARRIOR GULF & FROM MIKE BOX BR TO SOUTHERN IONIX | Other | $42,800 |
ALABAMA | MOBILE | RESURFACE BAKER RD FROM I65 TO SR13 (US43) | Other | $19,422 |
ALABAMA | MOBILE | WIDEN, RESURFACE, & CULVERT IMPROVEMENTS ON CR-24 (HALF-MILE RD.) FROM CR-225 (BEVERLY RD.) TO 0.17 MILE WEST OF CR-23 SOUTH (PADGETT SWITCH RD. SOUTH) MCP 49-66-07 | Pavement Improvement | $265,000 |
ALABAMA | COLUMBUS (GA) | RESURFACING AND STRIPING CR-427 (PIERCE ROAD) FROM SR-1 (US-431/280) IN RUSSELL TO CR-248 (SUMMERVILLE RD) IN LEE COUNTY, LCP 41-105-09 | Other | $37,500 |
ALABAMA | DECATUR | RESURFACE AUSTIINVILLE RD FROM CARRIDALE ST TO 14TH ST SW TO CENTERAL PW IN THE CITY OF DECATUR | Other | $6,943 |
ALABAMA | DOTHAN | RESURFACE WESTGATE PARKWAY FROM SR12 (US84) TO SR53 (US231) | Other | $78,000 |
ALABAMA | DOTHAN | RESURFACING HONEYSUCKLE RD FROM SR12 (US84) TO CR15 (PARK AVE) | Other | $95,000 |
ALABAMA | DIVISION WIDE SPOT REPAIRS PLANING AND RESURFACING | Pavement Improvement | $760,611 | |
ALABAMA | MONTGOMERY | RESURFACE SR-14 FROM SR-212 TO SR-9 AND RESURFACE SR-212 FROM SR-14 TO SR-111 | Pavement Improvement | $1,541,477 |
ALABAMA | GADSDEN | I-59 CONCRETE PAVEMENT REHABILITATION WITH UNBONDED OVERLAY FROM 0.6 MILES SOUTH OF ATTALLA NORTH CITY LIMITS AT NB STATION 123+33.20 (MP. 183.811) TO THE END OF BRIDGE OVER CR-276 (STEPHEN GAP ROAD) | Pavement Improvement | $47,525,424 |
ALABAMA | FLORENCE | SHEFFIELD, IMPROVEMENTS TO SECOND AND FIRST STREETS FROM SR-2 (US-72, N JACKSON HWY) WEST TO MONTGOMERY AVE, RESURFACE S MONTGOMERY AVE FROM RR, SOUTH TO TUSCUMBIA CITY LIMITS, RESURFACE NE JACKSON HW | Other | $34,768 |
ALABAMA | MOBILE | ADJUST SIGNAL TIMING @ VARIOUS EXISTING TRAFFIC SIGNALS IN THE CITY OF MOBILE | Other | $149,500 |
ALABAMA | FLORENCE | MUSCLE SHOALS, RESURFACE GUSMUS AVE FROM SR-184 (2ND ST) TO AVALON AVE, S BROADWAY AVE FROM CR-24 (W 6TH ST) TO AVALON AVE & CR-24 (W 6TH ST) FROM GEORGE WALLACE BLVD TO SR-2 (US-72,WOODWARD AVE) | Other | $33,359 |
ALABAMA | HUNTSVILLE | RESURFACING VARIOUS ELIGIBLE STREETS IN THE CITY OF HUNTSVILLE, PHASE 2 (STATE SUPPORT SERVICES) | Other | $64,974 |
ALABAMA | HUNTSVILLE | RESURFACING VARIOUS ELIGIBLE STREETS IN THE CITY OF HUNTSVILE, PHASE 1 (STATE SUPPORT SERVICES) | Other | $150,726 |
ALASKA | KOTZEBUE - SHORE AVENUE, PE | Pavement Improvement | $6,500,000 | |
ALASKA | GUSTAVUS CAUSEWAY, PE. 03/20/2007 - Scope Revision | Bridge Improvement | $7,700,000 | |
ALASKA | Repave the bike path along the Richardson Highway from Egan Drive to Robe River Subdivision (7miles). The project will also rehabilitate and pave the access road to the Blueberry Lake Campground. | Pavement Improvement | $1,243,248 | |
ALASKA | Repave the bike path along the Richardson Highway from Egan Drive to Robe River Subdivision (7miles). The project will also rehabilitate and pave the access road to the Blueberry Lake Campground. | Pavement Improvement | $701,463 | |
ALASKA | Sterling Highway Resurfacing: Soldotna to N. Coho Loop (ES) | Pavement Improvement | $7,584,100 | |
ALASKA | Kodiak: Rezanof Drive - Coast Guard Access Road to Marine Way. 6.4 Miles | Pavement Improvement | $7,138,763 | |
ALASKA | ANCHORAGE | Resurface stripe Jewel Lake Road from its intersection with Dimond Blvd to its intersection at 63rd Ave. | Other | $100,000 |
ALASKA | Revised scope to add with enhancements, name change: Denali HWY MP 7 Wayside | Transportation Enhancements | $498,856 | |
ALASKA | Juneau Glacier Highway - Amalga Harbor to Eagle Beach Kayak Launch (4/28/08 Provide for bicycles and peds) | Pavement Improvement | $12,074,972 | |
ALASKA | Pavement rehabilitation on Egan Drive from Mendenhall Loop Road to Brotherhood Bridge. Juneau, AK | Pavement Improvement | $4,000,000 | |
ALASKA | Haines Highway from the intersections of Front Street to Union Street | Pavement Improvement | $2,719,460 | |
ALASKA | New weighing system facility to faclitate simultaneous axle group and gross weight indications for truck weight enforcement. | New Construction | $3,750,000 | |
ALASKA | Rehabilitate portions of the Glenn Highway to remove rutted section of highway. Includes guardrail repair or replacement and terminal end upgrades. | Pavement Improvement | $2,037,579 | |
ALASKA | ANCHORAGE | Glenn Highway, Hiland Interchange to Eklutna RR Overcrossing, 15.2 Miles Resurfacing | Pavement Improvement | $13,742,683 |
ALASKA | Rehabilitate pavement, widen shoulders, build passing lanes and construct safety improvements as needed. Provide for public wayside. | Pavement Improvement | $25,175,000 | |
ARIZONA | YUMA (CA) | Chain Link Fence | Other | $784,200 |
ARIZONA | PHOENIX, AZ | Widen Roadway | Pavement Widening | $34,915,219 |
ARIZONA | Widen Roadway | Pavement Improvement | $28,615,868 | |
ARIZONA | TI Reconstruction | Pavement Widening | $16,949,440 | |
ARIZONA | Pavement Preservation | Pavement Improvement | $5,204,598 | |
ARIZONA | Replace Barb Wire Fence | Other | $478,236 | |
ARIZONA | Pavement Preservation | Pavement Improvement | $7,033,993 | |
ARIZONA | Pavement Preservation | Pavement Improvement | $2,232,218 | |
ARIZONA | Widen Roadway | Pavement Widening | $19,173,808 | |
ARIZONA | Replace Barb Wire Fence | Other | $183,636 | |
ARIZONA | Replace Barb Wire Fence | Other | $427,181 | |
ARIZONA | Replace Barb Wire Fence | Other | $414,305 | |
ARIZONA | Chain Link Fence | Other | $487,651 | |
ARIZONA | Replace Barb Wire Fence | Other | $786,039 | |
ARIZONA | Micro Seal | Pavement Improvement | $536,841 | |
ARIZONA | Reconstruct Roadway | Pavement Improvement | $11,614,305 | |
ARIZONA | Scour Retrofit | Bridge Improvement | $247,576 | |
ARIZONA | Bridge Rehabilitation | Bridge Improvement | $438,000 | |
ARIZONA | Micro Seal | Pavement Improvement | $397,616 | |
ARIZONA | PHOENIX, AZ | Widen Roadway | Pavement Widening | $10,579,699 |
ARIZONA | PHOENIX, AZ | Gateway graphics | Transportation Enhancements | $825,998 |
ARIZONA | PHOENIX, AZ | Gateway graphics | Transportation Enhancements | $813,000 |
ARIZONA | Pavement Preservation | Pavement Improvement | $10,530,238 | |
ARIZONA | Pavement Preservation | Pavement Improvement | $3,541,615 | |
ARIZONA | Pavement Preservation | Pavement Improvement | $2,500,489 | |
ARIZONA | Intersection Improvement | Pavement Improvement | $196,896 | |
ARIZONA | Replace Barb Wire Fence | Other | $835,226 | |
ARIZONA | Pavement Preservation | Pavement Improvement | $1,063,943 | |
ARIZONA | Replace Barb Wire Fence | Other | $807,612 | |
ARIZONA | Pavement Preservation | Pavement Improvement | $2,596,246 | |
ARIZONA | PHOENIX, AZ | Widen Roadway | Pavement Widening | $18,249,678 |
ARIZONA | Widen Roadway | Pavement Improvement | $3,266,598 | |
ARIZONA | TUCSON | Pavement Preservation | Pavement Improvement | $3,396,008 |
ARIZONA | TUCSON | Bridge Deck Rehab | Bridge Improvement | $191,204 |
ARIZONA | Widen Roadway | Pavement Improvement | $2,613,583 | |
ARIZONA | Widen Roadway | Pavement Improvement | $4,467,293 | |
ARIZONA | Replace Barb Wire Fence | Other | $890,664 | |
ARIZONA | FLAGSTAFF | Pavement Preservation | Pavement Improvement | $4,677,804 |
ARIZONA | Cst Parallel Road | New Construction | $12,302,956 | |
ARIZONA | YUMA (CA) | Widen Roadway | Pavement Widening | $11,500,000 |
ARIZONA | Pavement Preservation | Pavement Improvement | $13,464,426 | |
ARIZONA | Chip Seal | Pavement Improvement | $633,688 | |
ARIZONA | Construct Passing Lanes | Pavement Improvement | $1,979,660 | |
ARIZONA | TUCSON | Various locations in Oro Valley, AZ; PE for Installation of Fog Seals, Micro Surfaces, Mill & Inlays. | Other | $10,000 |
ARIZONA | PHOENIX, AZ | TI Improvement | New Bridge Construction | $8,239,577 |
ARIZONA | Pavement Preservation | Pavement Improvement | $3,536,716 | |
ARIZONA | Pavement Preservation | Pavement Widening | $6,721,707 | |
ARIZONA | Pavement Preservation | Pavement Improvement | $3,692,604 | |
ARIZONA | Replace Barb Wire Fence | Other | $1,003,925 | |
ARIZONA | PHOENIX, AZ | Widen Roadway | Pavement Improvement | $523,515 |
ARIZONA | Intersection Improvement | Pavement Improvement | $1,014,403 | |
ARIZONA | Pavement Preservation | Pavement Improvement | $3,014,598 | |
ARIZONA | Pedestian lighting and plantings | Pavement Improvement | $367,919 | |
ARIZONA | Slurry Seal | Pavement Improvement | $446,670 | |
ARIZONA | Micro Seal | Pavement Improvement | $1,264,046 | |
ARIZONA | Chip Seal | Pavement Improvement | $832,049 | |
ARIZONA | Chip Seal | Pavement Improvement | $712,488 | |
ARIZONA | Pavement Preservation | Other | $20,000 | |
ARIZONA | Design and Reconstruction of Pavement | Other | $20,000 | |
ARIZONA | PHOENIX, AZ | Preliminary engineering, design and construction for Mill & Replace | Other | $20,352 |
ARIZONA | PHOENIX, AZ | Preliminary engineering, design and construction for Mill & Replace | Other | $3,594 |
ARIZONA | PHOENIX, AZ | Pre-engineer/Design and Pavement Rehabiliation and Preservation | Other | $16,219 |
ARIZONA | Mill and fill existing deteriorating asphalt pavement | Other | $20,000 | |
ARIZONA | Pavement Preservation | Other | $30,000 | |
ARIZONA | FLAGSTAFF | Pavement Preservation | Other | $40,000 |
ARIZONA | PHOENIX, AZ | Pre-engineer/Design and construct Pedestrian crossing | Other | $3,500 |
ARIZONA | PHOENIX, AZ | Pre-engineer/Design and construct, repair and restoration of Cave Creek Road | Other | $55,334 |
ARIZONA | PHOENIX, AZ | Intersection and Capacity Improvement | Other | $43,645 |
ARIZONA | PHOENIX, AZ | Design and reconstruction of pavement | Other | $91,842 |
ARIZONA | Intersection Traffic Signals | Other | $20,000 | |
ARIZONA | Pavement Preservation | Other | $50,000 | |
ARIZONA | PHOENIX, AZ | Pre-Engineer/Design and Mill and Replace Existing Road. | Other | $9,528 |
ARIZONA | FLAGSTAFF | Pathway and landscaping | Transportation Enhancements | $613,298 |
ARIZONA | PHOENIX, AZ | ALONG SHEA BLVD FROM PALISADES BLVD TO FOUNTAIN HILLS BLVD IN THE TOWN OF FOUNTAIN HILLS, AZ---ARRA | Other | $45,087 |
ARIZONA | PHOENIX, AZ | Design and Construct Pedestrian and Landscape Improvements | Other | $10,185 |
ARIZONA | PHOENIX, AZ | Design and Construct Signage Improvements | Other | $1,650 |
ARIZONA | PHOENIX, AZ | Pre-Engineer/Design and construct mill, patch and replace | Other | $15,648 |
ARIZONA | Bridge Rehabilitation | Other | $20,000 | |
ARIZONA | PHOENIX, AZ | Pre-Engineer/Design and Construct Nova Chip Overlays- arterial roadways | Other | $187,250 |
ARIZONA | PHOENIX, AZ | Pre-Engineer/Design and construct pavement overlay | Other | $11,700 |
ARIZONA | PHOENIX, AZ | Pre-Engineer/Design and construct pavement surface treatment | Other | $10,200 |
ARIZONA | PHOENIX, AZ | Install thermoplastic pavement markings | Other | $7,168 |
ARIZONA | PHOENIX, AZ | Install wireless communication with traffic signals | Other | $6,900 |
ARIZONA | PHOENIX, AZ | Install wireless communication with traffic signals | Other | $6,000 |
ARIZONA | PHOENIX, AZ | CCTV Camera Installations | Other | $2,700 |
ARIZONA | PHOENIX, AZ | Modernize traffic signals | Other | $11,000 |
ARIZONA | PHOENIX, AZ | New traffic signal cabinets and controllers | Other | $11,000 |
ARIZONA | PHOENIX, AZ | Pre-Engineer/Design and Construct Pavement Rehab projects | Other | $11,227 |
ARIZONA | TUCSON | SAN XAVIER ROAD BETWEEN MISSION AND LOS REALES ROADS ON TOHONO O'ODHAM NATION | Other | $10,000 |
ARIZONA | FLAGSTAFF | Mill and repave intersection | Other | $2,000 |
ARIZONA | Street overlay / pavement preservation | Other | $10,000 | |
ARIZONA | 2" Overlay | Other | $6,000 | |
ARIZONA | PHOENIX, AZ | Pre-Engineer/Design and mill and replace pavement resurfacing/ reconstruction | Other | $12,279 |
ARIZONA | Intersection signalization | Other | $20,000 | |
ARIZONA | ALONG MOHAVE CHANNEL BETWEEN GORDON DRIVE AND BANK STREET IN THE CITY OF KINGMAN, ARIZONA | Transportation Enhancements | $698,368 | |
ARIZONA | ALONG MOHAVE CHANNEL BETWEEN BANK STREET AND NORTHERN AVENUE IN THE CITY OF KINGMAN, AZ; SHARED USE PATHWAY---ARRA | Transportation Enhancements | $440,000 | |
ARIZONA | MILL & REPLACE; NORTHERN AVE; STOCKTON HILL RD TO BANK STREET IN KINGMAN, AZ | Other | $20,000 | |
ARIZONA | Pave existing shoulders and add bike lane | New Construction | $750,000 | |
ARIZONA | PHOENIX, AZ | Pre-Engineer/Design and construct AR Overlay | Other | $59,508 |
ARIZONA | TUCSON | Pavement Preservation | Other | $10,000 |
ARIZONA | Pavement Preservation | Other | $40,000 | |
ARIZONA | PHOENIX, AZ | Beardley Road; Lake Pleasant road to 83rd Ave in Peoria; Preliminary Engineering; | Other | $11,301 |
ARIZONA | PHOENIX, AZ | BEARDSLEY ROAD CONNECTION; Loop 101 to Beardsley Road at 83rd ave.Lake Pleasant Pkwy in Peoria. Preliminary Engineering | Other | $28,504 |
ARIZONA | PHOENIX, AZ | Design & Construction of Intersection Improvements | Other | $27,693 |
ARIZONA | PHOENIX, AZ | Design & Construction of Removal/Replacement of Existing ADA Ramps or Construction of New ADA Ramps | Other | $82,550 |
ARIZONA | PHOENIX, AZ | Design & Construction of Removal/Replacement of Existing ADA Ramps or Construction of New ADA Ramps | Other | $82,550 |
ARIZONA | PHOENIX, AZ | Design & Costruct Bridge Deck Rehabilitations | Other | $187,106 |
ARIZONA | PHOENIX, AZ | Design & Costruct Bridge Joint Rehabilitations | Other | $184,883 |
ARIZONA | PHOENIX, AZ | Design &Procure/Install CCTV | Other | $141,205 |
ARIZONA | PHOENIX, AZ | Design & Procure/Install Fiber Optic Backbone System | Other | $91,334 |
ARIZONA | PHOENIX, AZ | Design &Procure/Install Wireless Communications | Other | $106,654 |
ARIZONA | PHOENIX, AZ | Inventory / Programming & Procure / Install Traffic Control Signs | Other | $226,668 |
ARIZONA | PHOENIX, AZ | Design & Construction of Pavement Preservation | Other | $91,786 |
ARIZONA | PHOENIX, AZ | Design & Construction of Pavement Preservation | Other | $91,786 |
ARIZONA | PHOENIX, AZ | Design & Construction of Pavement Preservation | Other | $91,786 |
ARIZONA | TUCSON | Paved shoulders, shared use driveway improvements, access ramps | New Construction | $575,000 |
ARIZONA | TUCSON | Pavement Preservation | Other | $74,690 |
ARIZONA | TUCSON | Structural deck repairs performed from above & between parapet walls. | Other | $60,000 |
ARIZONA | FLAGSTAFF | Overlay/ 3" AC | Other | $20,000 |
ARIZONA | La Villita in Rancho Sahuarita, and Duval Mine Road from La Canada to west town limits in SAHUARITA- Pavement Pres. and Pathway. | Other | $10,000 | |
ARIZONA | Pavement Preservation | Other | $40,000 | |
ARIZONA | TUCSON | Pavement Preservation | Other | $10,000 |
ARIZONA | Pavement Preservation | Other | $20,000 | |
ARIZONA | PHOENIX, AZ | Pre-Engineer/Design and construct pavement Reconstruction and ITS Conduit Installation | Other | $29,334 |
ARIZONA | Multi use path, landscaping, and irrigation | Other | $650,000 | |
ARIZONA | Widening, signal upgrades, drainage, improvements, curb, sidewalk, MUP on S side. | Other | $20,000 | |
ARIZONA | 2" AC Overlay | Other | $20,000 | |
ARIZONA | TUCSON | Pavement Preservation | Other | $71,700 |
ARIZONA | PHOENIX, AZ | Design and Complete Pavement Mill and Replace | Other | $12,883 |
ARIZONA | San Luis II Port of Entry, Avenue E and County 25th Street Preliminary Engineering | New Construction | $20,127 | |
ARIZONA | PHOENIX, AZ | Pre-Engineer/Design and construct mill and replace - pavement resurfacing | Other | $12,918 |
ARIZONA | YUMA (CA) | Construction of an interpretative plaza, complete with retaining walls | New Construction | $750,000 |
ARIZONA | Cold in place recycle; reconstruction | Other | $20,000 | |
ARKANSAS | PROVIDE GRADING AND STRUCTURES FOR 9.89 MILES OF A 4-LANE DIVIDED FACILITY ON NEW LOCATION | New Construction | $21,094,279 | |
ARKANSAS | CONTINUE MODIFICATION OF EXISTING INTERCHANGE | Bridge Improvement | $15,991,380 | |
ARKANSAS | ACHM REHABILITATION OF 4.30 MILES | Pavement Improvement | $1,663,847 | |
ARKANSAS | ACHM REHABILITATION OF 1.36 MILES | Pavement Improvement | $438,262 |
Source: FDIC