Road and bridge projects are expected to make up one of the biggest chunks of the jobs created in the stimulus package. Below, you’ll find a chart of more than 5,800 projects that have been approved by the U.S. Department of Transportation. Once given the green light, states can put the projects out to bid, contract them and begin construction work. So far, about 2,300 projects are under way.

Help us find out how much progress has been made on these projects by participating in our Stimulus Spot Check.

For more on the stimulus, check out our blog and resource page.

1 / 24
State Urban Area Project Description Improvement Type ARRA Funds Obligated
ALABAMA HUNTSVILLE SR-1 (MEMORIAL PKY) FR CR-85 (OAKWOOD AV) TO CR-22 (SPARKMAN DR) INCLUDING AN OVERPASS AT CR-22 (PRIORITY #9-2008) Pavement Improvement $25,534,292
ALABAMA DOTHAN RETROFIT BRIDGE RAILS ON SR-1 (US-231) AT BIN 006900 AND 006901 @ BIG CREEK Pavement Improvement $154,446
ALABAMA DOTHAN RESURFACE SR-1 (US-231) FROM FLORIDA STATE LINE TO END OF PAVED SHOULDERS NORTH OF CR-93 Pavement Improvement $2,850,120
ALABAMA RESURFACE SR-1 (US-431) FROM HEADLAND SOUTH CITY LIMIT TO NORTH OF SR-173 Pavement Improvement $2,209,099
ALABAMA COLUMBUS (GA) RESURFACE SR-1 (US-431) FROM CR-137 (OLD SEALE HWY) TO 0.6 MILE SOUTH SR-38 (US-280), FY 2009 PHASE 2, Pavement Improvement $5,821,097
ALABAMA WIDENING & RESURFACING SR-1 (US-431) FROM NORTH END OF THE TENN. RIVER BRIDGE TO CR-5 (CATHEDRAL CAVERNS HWY) Pavement Improvement $3,761,469
ALABAMA FLORENCE RESURFACE & 2 FT. PAVEMENT WIDENING SR-2 (US-72) FROM 0.6 MILE WEST CANE CREEK TO 0.449 MILE EAST OF DRY Pavement Improvement $1,659,388
ALABAMA RESURFACING AND PAVEMENT WIDENING SR-3 (US-31) FROM JUST SOUTH OF CACTUS STREET TO I-65 NEAR CITY OF ATHENS Pavement Improvement $1,220,429
ALABAMA RESURFACING SR-3 (US-31) FROM 0.24 MILE NORTH OF SR-59 INTERSECTION IN STAPLETON TO BAY MINETTE SOUTH CITY LIMITS Pavement Improvement $2,886,968
ALABAMA RESURFACE & 2' WIDENING ON SR-3 (US-31) FROM CONECUH COUNTY LINE TO 0.8 MILE NORTH PERSIMMON CREEK (FY2009 PHASE2) Pavement Improvement $2,335,367
ALABAMA RESURFACE & 2' WIDENING ON SR-3 (US-31) FROM JUNCTION OF SR-185 TO MONTGOMERY COUNTY LINE (FY2009 PHASE2) Pavement Improvement $4,383,448
ALABAMA RESURFACING SR-3 (US-31) FROM SR-12 (US-84) TO BUTLER COUNTY LINE. FY 2009 PHASE 2 Pavement Improvement $2,453,411
ALABAMA PLANING RESURFACE AND TRAFFIC STRIPE SR-5 FROM SR-13(US-43) TO WILCOX COUNTY LINE 2009 PHASE 1 Pavement Improvement $1,619,174
ALABAMA MONTGOMERY RESURFACE & 2' WIDENING ON SR-6 (US-82) FROM JUST WEST OF CR-40 TO SR-206 Pavement Improvement $4,938,746
ALABAMA TUSCALOOSA RESURFACE SR-7 (US-11) FROM GREENE COUNTY LINE TO JUST SOUTH OF WARRIOR RIVER BRIDGE AT FOSTERS AND HOLLY SPRINGS ROAD FROM SR-7 (US-11) TO JUST SOUTH OF THE I-20/59 INTERCHANGE Pavement Improvement $4,415,517
ALABAMA PLANING, PAVEMENT WIDENING AND RESURFACING SR-7 (US-11) FROM NORTH OF CR-208 (GREENETRACK RD.) TO TUSCALOOSA COUNTY LINE. FY2009 PHASE 2 Pavement Improvement $3,357,073
ALABAMA RESURFACE & 2' WIDENING ON SR-8 (US-80) FROM NEAR JUNCTION OF SR-186 TO LEE COUNTY LINE (FY2010 PHASE1) Pavement Improvement $3,198,619
ALABAMA RESURFACING AND TRAFFIC STRIPE ON SR-10 FROM SR-28 TO SR-41, FY2009 PHASE 2; Pavement Improvement $720,697
ALABAMA RESURFACING AND PAVEMENT WIDENING ON SR-10 FROM BUTLER COUNTY LINE TO SR-9 (US-331). FY2010 PHASE 1 Pavement Improvement $2,981,219
ALABAMA RESURFACE ON SR-15 (US-29) FROM SR-197 TO SR-6 (US-82) (FY2009 PHASE II) Pavement Improvement $512,187
ALABAMA AUBURN-OPELIKA RESURFACING SR-15 (US-29) FROM MACON COUNTY TO SOUTH CR-010 (SAND HILL RD), FY2009 PHASE 2 Pavement Improvement $908,101
ALABAMA WIDENING, RESURFACING & TRAFFIC STRIPE SR-17 FROM 1.3 MILES SOUTH CR-18 TO 0.7 MILES NORTH OF CR-28 Pavement Improvement $1,321,334
ALABAMA RESURFACING & TRAFFIC STRIPE ON SR-17 FROM 0.7 MI NORTH OF CR-28 TO NORTH OF SOUTH BUTLER CITY LIMITS Pavement Improvement $1,257,489
ALABAMA PLANE/RESURFACE SR-17 FROM 0.7 MILE NORTH CR-29 TO CR-30 IN SULLIGENT, FY2009 PHASE 2 Pavement Improvement $6,084,240
ALABAMA RESURFACING AND STRIPING SR-17 FROM LAMAR COUNTY LINE TO SR-4 Pavement Improvement $1,770,060
ALABAMA FY 2010 PHASE 1, PLANING AND RESURFACING ON SR-17 FROM SR-28 TO CR-24 Pavement Improvement $2,709,873
ALABAMA FY 2010 PHASE 1, PLANING AND RESURFACING ON SR-17 FROM 1.7 MILES SOUTH OF CR-20 TO SR 56, IN CHATOM Pavement Improvement $3,517,300
ALABAMA RESURFACE SR17 FROM SOUTH CITY LMITIES OF CARROLTON TO 0.6 MILE NORTH CARROLLTON NORTH CITY LIMITS IN PICKENS CO Pavement Improvement $1,944,144
ALABAMA RESURFACE SR-20 FROM THE TENNESSEE STATE LINE TO SOUTH OF CR-22 AT THE NATCHEZ TRACE PARKWAY; PHASE II RESURFACING BUDGET Pavement Improvement $2,195,023
ALABAMA RESURFACING AND TRAFFIC STRIPE ON SR-21 FROM NORTH END OF LITTLE RIVER BRIDGE @ COUNTY LINE TO NORTH OF CR-8, FY2009 PHASE 2; Pavement Improvement $2,344,547
ALABAMA RESURFACE AND TRAFFIC STRIPE ON SR-21 FROM NORTH OF CR-8 TO SOUTH OF CR-10, FY2009 PHASE 2; Pavement Improvement $2,264,245
ALABAMA RESURFACING SR-21 FROM THE FLORIDA STATE LINE TO MP 0.968, FY 2009 PHASE 2 Pavement Improvement $368,368
ALABAMA RESURFACE SR-21 FROM CR-947 (MAXWELLBORN RD) TO NEAR FOOTHILLS DR, FY 2009 PHASE 2 Pavement Improvement $1,898,929
ALABAMA RESURFACE & 2' WIDENING ON SR-22 FROM SR-5 TO SR-219 (FY2010 PHASE1) Pavement Improvement $5,225,138
ALABAMA RESURFACE SR-24 FROM CR-460 TO NEAR CR-320. FY 2009 PHASE II RESURFACING BUDGET Pavement Improvement $3,792,260
ALABAMA PLANING, PAVEMENT WIDENING AND RESURFACING SR-25 FROM CR-29 TO BIBB COUNTY LINE, FY2009 PHASE 2 Pavement Improvement $1,905,541
ALABAMA RESURFACING AND PAVEMENT WIDENING ON SR-27 FROM INDEGO PL TO DALE COUNTY LINE (FY2009 PHASE 2) Pavement Improvement $1,718,249
ALABAMA RESURFACE SR-33 FROM SR-74 TO NORTH END OF SIPSEY RIVER BRIDGE Pavement Improvement $2,021,675
ALABAMA 2' PAVEMENT WIDENING & RESURFACING SR-35 FROM SR-79 INTERSECTION WESTERLY THROUGH WOODVILLE TO THE JUNCTION OF SR-2 (US-72) Pavement Improvement $1,376,799
ALABAMA DECATUR 2' PAVEMENT WIDENING AND RESURFACING SR-36 FROM INTERSECTION WITH US-31 (SR-3) IN HARTSELLE AT MP 21.15 TO I-65 INTERCHANGE AT MP 23.55. FY 2010 PHASE 1 RESURFACING PROGRAM Pavement Improvement $974,234
ALABAMA BIRMINGHAM RESURFACE SR-38 (US-280) FROM CR-353 (HUGH DANIEL DR) TO CR-280 (OLD US 280) Pavement Improvement $6,551,704
ALABAMA RESURFACE SR-49 FROM TALLAPOOSA COUNTY LINE TO SR-77, FY 2009 PHASE 2 Pavement Improvement $2,355,118
ALABAMA RESURFACING AND PAVEMENT WIDENING ON SR-51 FROM JUST SOUTH OF SR-239 TO THE BULLOCK COUNTY LINE (FY2009 PHASE 2) Pavement Improvement $2,852,842
ALABAMA RETROFIT BRIDGE RAILS ON SR-53 (US-231) AT BIN 005532, 005533 (LITTLE CLAYBANK CREEK) & 005571, 009388 (BEAR CREEK) Bridge Improvement $102,730
ALABAMA RESURFACE SR-53 (US-231) FROM 0.2 MILE SOUTH OF SR-27 TO 0.06 MILE NORTH OF CR-2 Pavement Improvement $2,768,226
ALABAMA RESURFACING SR-53 (US-231) FROM NORTH OF I-20 TO 2.7 MILES NORTH OF WATTSVILLE Pavement Improvement $1,824,034
ALABAMA RESURFACE SR-55 FROM SR-12 (US-84) TO NORTH CITY LIMITS OF RED LEVEL (FY 2009 PHASE 2) Pavement Improvement $2,290,656
ALABAMA RESURFACE SR-55 FROM CONECUH COUNTY LINE TO SR-3 (US-31) (FY2009 PHASE2) Pavement Improvement $579,840
ALABAMA WIDEN SR-69 FROM SR-13 (US-43) TO HALE COUNTY LINE Pavement Improvement $1,012,013
ALABAMA RESURFACING SR-69 FROM I-65 IN GOOD HOPE TO SR-3 (US-31) IN CULLMAN Pavement Improvement $1,614,641
ALABAMA 2 FT. SAFETY WIDENING, RESURFACE, AND CULVERT EXTENSION ON SR-69 FROM MARENGO/HALE COUNTY LINE TO SR-8 (US-80), FY2009 PHASE 2 Pavement Improvement $570,127
ALABAMA RESURFACE & TRAFFIC STRIPE SR-69 FROM SR-13 (US-43) TO HALE COUNTY LINE Pavement Improvement $3,424,090
ALABAMA RESURFACE, STRIPING SR-75 FROM CR-363 (BROOKS LANE) IN ALLGOOD TO CR-58 (2ND ST) IN ONEONTA Pavement Improvement $1,783,600
ALABAMA BIRMINGHAM PLANING, RESURFACING SR-79 FROM WINEWOOD ROAD TO SR-151 Pavement Improvement $2,606,952
ALABAMA RESURFACE SR-93 FROM SR-53 (US-231) TO THE NORTH CITY LIMITS OF BRUNDIDGE (FY 2009 PHASE 2) (CSX RR) Pavement Improvement $772,677
ALABAMA MONTGOMERY RESURFACE & 2' WIDENING ON SR-97 FROM CRENSHAW COUNTY LINE TO NORTH OF JUNCTION OF SR-3 (US-31) (FY2009 PHASE2) Pavement Improvement $729,364
ALABAMA RESURFACING AND PAVEMENT WIDENING ON SR-103 FROM THE FLORIDA STATE LINE TO SR-52 IN SLOCOMB (FY 2009 PHASE 2) Pavement Improvement $2,606,280
ALABAMA RESURFACE SR-115 FROM SR-9 TO SR-38 (US-280), FY 2009 PHASE 2 Pavement Improvement $1,299,848
ALABAMA RESURFACE SR-118 FROM 4TH STREET IN CARBON HILL TO CR-298 (RIPLEY LOOP ROAD) Pavement Improvement $1,478,787
ALABAMA RESURFACE SR-129 FROM SR-171 (US-43) TO CR-49 IN HUBBERTVILLE, 2009 PHASE II Pavement Improvement $1,577,067
ALABAMA RESURFACE SR-139 FROM SIX MILE CREEK TO 0.100 MILE NORTH OF SHELBY COUNTY LINE, FY2010 PHASE I Pavement Improvement $2,791,631
ALABAMA RESURFACING, SR 148, 2'WIDENING AND STRIPING FROM SR 21 TO EAST CITY LIMITS OF SYLACAUGA Pavement Improvement $709,237
ALABAMA PLANING, PAVEMENT WIDENING AND RESURFACING SR-155 FROM NEAR CR-33 TO SHELBY COUNTY LINE . FY2009 PHASE 2 Pavement Improvement $2,007,167
ALABAMA FLORENCE RESURFACING, STRIPING, AND BRIDGE RAIL RETROFIT SR 157 FROM LAWRENCE COUNTY LINE TO SR 20. FY 2009 ECONOMIC STIMULUS PROJECT. Pavement Improvement $4,097,292
ALABAMA PLANING, PAVEMENT WIDENING AND RESURFACING SR-175 FROM SR-14 NEAR HEIBERGER TO SR-5, FY2009 PHASE 2 Pavement Improvement $2,142,465
ALABAMA ANNISTON ANNISTON E. BYPASS FROM 1500' SOUTH OF LAKE YAHOU TO SR-1 (US-431) ; GRADE DRAIN BRIDGE PARTIAL BASE AND PAVE New Construction $46,770,227
ALABAMA MOBILE PAVEMENT WIDENING & RESURFACING ON SR-213 FROM SR-158 TO SR-13 (US-43) Pavement Improvement $691,974
ALABAMA RESURFACE & 2' WIDENING ON SR223 FROM BULLOCK CO HIGH SCHOOL TO JUNCTION OF SR 6 (US82) FY2009 PHASE 2 Pavement Improvement $486,931
ALABAMA RESURFACING AND STRIPING SR 241 FROM JUST SOUTH OF THE MARION COUNTY LINE TO SR 237 Pavement Improvement $319,306
ALABAMA WIDENING & RESURFACING SR-273 FROM SR-68 IN LEESBURG TO AL-35 NEAR BLANCHE. FY 2009 PHASE 2 RESURFACING PROGRAM Pavement Improvement $5,743,428
ALABAMA FULL DEPTH RECLAMATION CR-267 FROM CR-222 IN FREDONIA TO SR-1 (US-431) SOUTH OF STROUD - CCP 09-09-01 Pavement Improvement $265,000
ALABAMA FLORENCE RESURFACING CR-57 FROM CR-61 TO SR-20 CCP 17-200-08 Pavement Improvement $382,520
ALABAMA RESURFACE CR-709 FROM SR-167 TO SR-134 CCP 16-05-07 Pavement Improvement $265,000
ALABAMA WIDEN & RESURFACE CR-99 FROM CR-41 TO CR-107 HCP 34-93-07 Pavement Improvement $265,000
ALABAMA BIN 003313 - BR ON CR-438 (E COOK RD.) @ CEDAR CREEK APPROX. 0.5 MILES NORTH OF ED TOLAR RD. (AASHTO) HCP 35-119-99 Bridge Replacement $265,000
ALABAMA DECATUR RESURFACE SOUTH SENECA DRIVE FROM TRINITY TOWN LIMITS TO DEANNA BRIDGE HIGHWAY (STATE SUPPORT SERVICES) Other $3,827
ALABAMA RESURFACING CR-2276 FROM CRENSHAW CO. LINE TO CR-2290 AND CR-2290 FROM CR-2276 TO CR-2262 IN HENDERSON PCP 55-98-07 Pavement Improvement $265,000
ALABAMA WIDEN & RESURFACE CR-82 FROM THE MEADOWS BRIDGE (LITTLE TALLAPOOSA RIVER) TO CR-87 - RCP 56-219-07 Pavement Improvement $265,000
ALABAMA BIRMINGHAM CR-97 (SHADES CREST RD) INTERSECTION IMPROVEMENT @ CR-42 (WEST OXMOOR RD) & TYLER RD, PH VII PROJECT SPONSOR CITY OF HOOVER Pavement Improvement $2,201,171
ALABAMA ANNISTON RESURFACE CR187 (FRIENDSHIP RD) FROM CR193 (BOILING SPRING RD) TO SR21 Other $67,600
ALABAMA MOBILE RESURFACE CR656 (SPRINGHILL AVE) FROM MCGREGOR AVE TO I65) Pavement Improvement $287,500
ALABAMA MOBILE RESURFACE CR656 (SPRINGHILL AVE) FROM I65 TO SR42 (US98 MOFFETT RD) Pavement Improvement $165,499
ALABAMA MOBILE RESURFACE WEST MAIN ST FROM PRICHARD AVE TO BRANCH AVE Other $75,887
ALABAMA MOBILE WIDEN & OVERLAY EXISTING LANES ON VIADUCT RD FROM EAST ON MIKE BOX BR TO WARRIOR GULF & FROM MIKE BOX BR TO SOUTHERN IONIX Other $42,800
ALABAMA MOBILE RESURFACE BAKER RD FROM I65 TO SR13 (US43) Other $19,422
ALABAMA MOBILE WIDEN, RESURFACE, & CULVERT IMPROVEMENTS ON CR-24 (HALF-MILE RD.) FROM CR-225 (BEVERLY RD.) TO 0.17 MILE WEST OF CR-23 SOUTH (PADGETT SWITCH RD. SOUTH) MCP 49-66-07 Pavement Improvement $265,000
ALABAMA COLUMBUS (GA) RESURFACING AND STRIPING CR-427 (PIERCE ROAD) FROM SR-1 (US-431/280) IN RUSSELL TO CR-248 (SUMMERVILLE RD) IN LEE COUNTY, LCP 41-105-09 Other $37,500
ALABAMA DECATUR RESURFACE AUSTIINVILLE RD FROM CARRIDALE ST TO 14TH ST SW TO CENTERAL PW IN THE CITY OF DECATUR Other $6,943
ALABAMA DOTHAN RESURFACE WESTGATE PARKWAY FROM SR12 (US84) TO SR53 (US231) Other $78,000
ALABAMA DOTHAN RESURFACING HONEYSUCKLE RD FROM SR12 (US84) TO CR15 (PARK AVE) Other $95,000
ALABAMA DIVISION WIDE SPOT REPAIRS PLANING AND RESURFACING Pavement Improvement $760,611
ALABAMA MONTGOMERY RESURFACE SR-14 FROM SR-212 TO SR-9 AND RESURFACE SR-212 FROM SR-14 TO SR-111 Pavement Improvement $1,541,477
ALABAMA GADSDEN I-59 CONCRETE PAVEMENT REHABILITATION WITH UNBONDED OVERLAY FROM 0.6 MILES SOUTH OF ATTALLA NORTH CITY LIMITS AT NB STATION 123+33.20 (MP. 183.811) TO THE END OF BRIDGE OVER CR-276 (STEPHEN GAP ROAD) Pavement Improvement $47,525,424
ALABAMA FLORENCE SHEFFIELD, IMPROVEMENTS TO SECOND AND FIRST STREETS FROM SR-2 (US-72, N JACKSON HWY) WEST TO MONTGOMERY AVE, RESURFACE S MONTGOMERY AVE FROM RR, SOUTH TO TUSCUMBIA CITY LIMITS, RESURFACE NE JACKSON HW Other $34,768
ALABAMA MOBILE ADJUST SIGNAL TIMING @ VARIOUS EXISTING TRAFFIC SIGNALS IN THE CITY OF MOBILE Other $149,500
ALABAMA FLORENCE MUSCLE SHOALS, RESURFACE GUSMUS AVE FROM SR-184 (2ND ST) TO AVALON AVE, S BROADWAY AVE FROM CR-24 (W 6TH ST) TO AVALON AVE & CR-24 (W 6TH ST) FROM GEORGE WALLACE BLVD TO SR-2 (US-72,WOODWARD AVE) Other $33,359
ALABAMA HUNTSVILLE RESURFACING VARIOUS ELIGIBLE STREETS IN THE CITY OF HUNTSVILLE, PHASE 2 (STATE SUPPORT SERVICES) Other $64,974
ALABAMA HUNTSVILLE RESURFACING VARIOUS ELIGIBLE STREETS IN THE CITY OF HUNTSVILE, PHASE 1 (STATE SUPPORT SERVICES) Other $150,726
ALASKA KOTZEBUE - SHORE AVENUE, PE Pavement Improvement $6,500,000
ALASKA GUSTAVUS CAUSEWAY, PE. 03/20/2007 - Scope Revision Bridge Improvement $7,700,000
ALASKA Repave the bike path along the Richardson Highway from Egan Drive to Robe River Subdivision (7miles). The project will also rehabilitate and pave the access road to the Blueberry Lake Campground. Pavement Improvement $1,243,248
ALASKA Repave the bike path along the Richardson Highway from Egan Drive to Robe River Subdivision (7miles). The project will also rehabilitate and pave the access road to the Blueberry Lake Campground. Pavement Improvement $701,463
ALASKA Sterling Highway Resurfacing: Soldotna to N. Coho Loop (ES) Pavement Improvement $7,584,100
ALASKA Kodiak: Rezanof Drive - Coast Guard Access Road to Marine Way. 6.4 Miles Pavement Improvement $7,138,763
ALASKA ANCHORAGE Resurface stripe Jewel Lake Road from its intersection with Dimond Blvd to its intersection at 63rd Ave. Other $100,000
ALASKA Revised scope to add with enhancements, name change: Denali HWY MP 7 Wayside Transportation Enhancements $498,856
ALASKA Juneau Glacier Highway - Amalga Harbor to Eagle Beach Kayak Launch (4/28/08 Provide for bicycles and peds) Pavement Improvement $12,074,972
ALASKA Pavement rehabilitation on Egan Drive from Mendenhall Loop Road to Brotherhood Bridge. Juneau, AK Pavement Improvement $4,000,000
ALASKA Haines Highway from the intersections of Front Street to Union Street Pavement Improvement $2,719,460
ALASKA New weighing system facility to faclitate simultaneous axle group and gross weight indications for truck weight enforcement. New Construction $3,750,000
ALASKA Rehabilitate portions of the Glenn Highway to remove rutted section of highway. Includes guardrail repair or replacement and terminal end upgrades. Pavement Improvement $2,037,579
ALASKA ANCHORAGE Glenn Highway, Hiland Interchange to Eklutna RR Overcrossing, 15.2 Miles Resurfacing Pavement Improvement $13,742,683
ALASKA Rehabilitate pavement, widen shoulders, build passing lanes and construct safety improvements as needed. Provide for public wayside. Pavement Improvement $25,175,000
ARIZONA YUMA (CA) Chain Link Fence Other $784,200
ARIZONA PHOENIX, AZ Widen Roadway Pavement Widening $34,915,219
ARIZONA Widen Roadway Pavement Improvement $28,615,868
ARIZONA TI Reconstruction Pavement Widening $16,949,440
ARIZONA Pavement Preservation Pavement Improvement $5,204,598
ARIZONA Replace Barb Wire Fence Other $478,236
ARIZONA Pavement Preservation Pavement Improvement $7,033,993
ARIZONA Pavement Preservation Pavement Improvement $2,232,218
ARIZONA Widen Roadway Pavement Widening $19,173,808
ARIZONA Replace Barb Wire Fence Other $183,636
ARIZONA Replace Barb Wire Fence Other $427,181
ARIZONA Replace Barb Wire Fence Other $414,305
ARIZONA Chain Link Fence Other $487,651
ARIZONA Replace Barb Wire Fence Other $786,039
ARIZONA Micro Seal Pavement Improvement $536,841
ARIZONA Reconstruct Roadway Pavement Improvement $11,614,305
ARIZONA Scour Retrofit Bridge Improvement $247,576
ARIZONA Bridge Rehabilitation Bridge Improvement $438,000
ARIZONA Micro Seal Pavement Improvement $397,616
ARIZONA PHOENIX, AZ Widen Roadway Pavement Widening $10,579,699
ARIZONA PHOENIX, AZ Gateway graphics Transportation Enhancements $825,998
ARIZONA PHOENIX, AZ Gateway graphics Transportation Enhancements $813,000
ARIZONA Pavement Preservation Pavement Improvement $10,530,238
ARIZONA Pavement Preservation Pavement Improvement $3,541,615
ARIZONA Pavement Preservation Pavement Improvement $2,500,489
ARIZONA Intersection Improvement Pavement Improvement $196,896
ARIZONA Replace Barb Wire Fence Other $835,226
ARIZONA Pavement Preservation Pavement Improvement $1,063,943
ARIZONA Replace Barb Wire Fence Other $807,612
ARIZONA Pavement Preservation Pavement Improvement $2,596,246
ARIZONA PHOENIX, AZ Widen Roadway Pavement Widening $18,249,678
ARIZONA Widen Roadway Pavement Improvement $3,266,598
ARIZONA TUCSON Pavement Preservation Pavement Improvement $3,396,008
ARIZONA TUCSON Bridge Deck Rehab Bridge Improvement $191,204
ARIZONA Widen Roadway Pavement Improvement $2,613,583
ARIZONA Widen Roadway Pavement Improvement $4,467,293
ARIZONA Replace Barb Wire Fence Other $890,664
ARIZONA FLAGSTAFF Pavement Preservation Pavement Improvement $4,677,804
ARIZONA Cst Parallel Road New Construction $12,302,956
ARIZONA YUMA (CA) Widen Roadway Pavement Widening $11,500,000
ARIZONA Pavement Preservation Pavement Improvement $13,464,426
ARIZONA Chip Seal Pavement Improvement $633,688
ARIZONA Construct Passing Lanes Pavement Improvement $1,979,660
ARIZONA TUCSON Various locations in Oro Valley, AZ; PE for Installation of Fog Seals, Micro Surfaces, Mill & Inlays. Other $10,000
ARIZONA PHOENIX, AZ TI Improvement New Bridge Construction $8,239,577
ARIZONA Pavement Preservation Pavement Improvement $3,536,716
ARIZONA Pavement Preservation Pavement Widening $6,721,707
ARIZONA Pavement Preservation Pavement Improvement $3,692,604
ARIZONA Replace Barb Wire Fence Other $1,003,925
ARIZONA PHOENIX, AZ Widen Roadway Pavement Improvement $523,515
ARIZONA Intersection Improvement Pavement Improvement $1,014,403
ARIZONA Pavement Preservation Pavement Improvement $3,014,598
ARIZONA Pedestian lighting and plantings Pavement Improvement $367,919
ARIZONA Slurry Seal Pavement Improvement $446,670
ARIZONA Micro Seal Pavement Improvement $1,264,046
ARIZONA Chip Seal Pavement Improvement $832,049
ARIZONA Chip Seal Pavement Improvement $712,488
ARIZONA Pavement Preservation Other $20,000
ARIZONA Design and Reconstruction of Pavement Other $20,000
ARIZONA PHOENIX, AZ Preliminary engineering, design and construction for Mill & Replace Other $20,352
ARIZONA PHOENIX, AZ Preliminary engineering, design and construction for Mill & Replace Other $3,594
ARIZONA PHOENIX, AZ Pre-engineer/Design and Pavement Rehabiliation and Preservation Other $16,219
ARIZONA Mill and fill existing deteriorating asphalt pavement Other $20,000
ARIZONA Pavement Preservation Other $30,000
ARIZONA FLAGSTAFF Pavement Preservation Other $40,000
ARIZONA PHOENIX, AZ Pre-engineer/Design and construct Pedestrian crossing Other $3,500
ARIZONA PHOENIX, AZ Pre-engineer/Design and construct, repair and restoration of Cave Creek Road Other $55,334
ARIZONA PHOENIX, AZ Intersection and Capacity Improvement Other $43,645
ARIZONA PHOENIX, AZ Design and reconstruction of pavement Other $91,842
ARIZONA Intersection Traffic Signals Other $20,000
ARIZONA Pavement Preservation Other $50,000
ARIZONA PHOENIX, AZ Pre-Engineer/Design and Mill and Replace Existing Road. Other $9,528
ARIZONA FLAGSTAFF Pathway and landscaping Transportation Enhancements $613,298
ARIZONA PHOENIX, AZ ALONG SHEA BLVD FROM PALISADES BLVD TO FOUNTAIN HILLS BLVD IN THE TOWN OF FOUNTAIN HILLS, AZ---ARRA Other $45,087
ARIZONA PHOENIX, AZ Design and Construct Pedestrian and Landscape Improvements Other $10,185
ARIZONA PHOENIX, AZ Design and Construct Signage Improvements Other $1,650
ARIZONA PHOENIX, AZ Pre-Engineer/Design and construct mill, patch and replace Other $15,648
ARIZONA Bridge Rehabilitation Other $20,000
ARIZONA PHOENIX, AZ Pre-Engineer/Design and Construct Nova Chip Overlays- arterial roadways Other $187,250
ARIZONA PHOENIX, AZ Pre-Engineer/Design and construct pavement overlay Other $11,700
ARIZONA PHOENIX, AZ Pre-Engineer/Design and construct pavement surface treatment Other $10,200
ARIZONA PHOENIX, AZ Install thermoplastic pavement markings Other $7,168
ARIZONA PHOENIX, AZ Install wireless communication with traffic signals Other $6,900
ARIZONA PHOENIX, AZ Install wireless communication with traffic signals Other $6,000
ARIZONA PHOENIX, AZ CCTV Camera Installations Other $2,700
ARIZONA PHOENIX, AZ Modernize traffic signals Other $11,000
ARIZONA PHOENIX, AZ New traffic signal cabinets and controllers Other $11,000
ARIZONA PHOENIX, AZ Pre-Engineer/Design and Construct Pavement Rehab projects Other $11,227
ARIZONA TUCSON SAN XAVIER ROAD BETWEEN MISSION AND LOS REALES ROADS ON TOHONO O'ODHAM NATION Other $10,000
ARIZONA FLAGSTAFF Mill and repave intersection Other $2,000
ARIZONA Street overlay / pavement preservation Other $10,000
ARIZONA 2" Overlay Other $6,000
ARIZONA PHOENIX, AZ Pre-Engineer/Design and mill and replace pavement resurfacing/ reconstruction Other $12,279
ARIZONA Intersection signalization Other $20,000
ARIZONA ALONG MOHAVE CHANNEL BETWEEN GORDON DRIVE AND BANK STREET IN THE CITY OF KINGMAN, ARIZONA Transportation Enhancements $698,368
ARIZONA ALONG MOHAVE CHANNEL BETWEEN BANK STREET AND NORTHERN AVENUE IN THE CITY OF KINGMAN, AZ; SHARED USE PATHWAY---ARRA Transportation Enhancements $440,000
ARIZONA MILL & REPLACE; NORTHERN AVE; STOCKTON HILL RD TO BANK STREET IN KINGMAN, AZ Other $20,000
ARIZONA Pave existing shoulders and add bike lane New Construction $750,000
ARIZONA PHOENIX, AZ Pre-Engineer/Design and construct AR Overlay Other $59,508
ARIZONA TUCSON Pavement Preservation Other $10,000
ARIZONA Pavement Preservation Other $40,000
ARIZONA PHOENIX, AZ Beardley Road; Lake Pleasant road to 83rd Ave in Peoria; Preliminary Engineering; Other $11,301
ARIZONA PHOENIX, AZ BEARDSLEY ROAD CONNECTION; Loop 101 to Beardsley Road at 83rd ave.Lake Pleasant Pkwy in Peoria. Preliminary Engineering Other $28,504
ARIZONA PHOENIX, AZ Design & Construction of Intersection Improvements Other $27,693
ARIZONA PHOENIX, AZ Design & Construction of Removal/Replacement of Existing ADA Ramps or Construction of New ADA Ramps Other $82,550
ARIZONA PHOENIX, AZ Design & Construction of Removal/Replacement of Existing ADA Ramps or Construction of New ADA Ramps Other $82,550
ARIZONA PHOENIX, AZ Design & Costruct Bridge Deck Rehabilitations Other $187,106
ARIZONA PHOENIX, AZ Design & Costruct Bridge Joint Rehabilitations Other $184,883
ARIZONA PHOENIX, AZ Design &Procure/Install CCTV Other $141,205
ARIZONA PHOENIX, AZ Design & Procure/Install Fiber Optic Backbone System Other $91,334
ARIZONA PHOENIX, AZ Design &Procure/Install Wireless Communications Other $106,654
ARIZONA PHOENIX, AZ Inventory / Programming & Procure / Install Traffic Control Signs Other $226,668
ARIZONA PHOENIX, AZ Design & Construction of Pavement Preservation Other $91,786
ARIZONA PHOENIX, AZ Design & Construction of Pavement Preservation Other $91,786
ARIZONA PHOENIX, AZ Design & Construction of Pavement Preservation Other $91,786
ARIZONA TUCSON Paved shoulders, shared use driveway improvements, access ramps New Construction $575,000
ARIZONA TUCSON Pavement Preservation Other $74,690
ARIZONA TUCSON Structural deck repairs performed from above & between parapet walls. Other $60,000
ARIZONA FLAGSTAFF Overlay/ 3" AC Other $20,000
ARIZONA La Villita in Rancho Sahuarita, and Duval Mine Road from La Canada to west town limits in SAHUARITA- Pavement Pres. and Pathway. Other $10,000
ARIZONA Pavement Preservation Other $40,000
ARIZONA TUCSON Pavement Preservation Other $10,000
ARIZONA Pavement Preservation Other $20,000
ARIZONA PHOENIX, AZ Pre-Engineer/Design and construct pavement Reconstruction and ITS Conduit Installation Other $29,334
ARIZONA Multi use path, landscaping, and irrigation Other $650,000
ARIZONA Widening, signal upgrades, drainage, improvements, curb, sidewalk, MUP on S side. Other $20,000
ARIZONA 2" AC Overlay Other $20,000
ARIZONA TUCSON Pavement Preservation Other $71,700
ARIZONA PHOENIX, AZ Design and Complete Pavement Mill and Replace Other $12,883
ARIZONA San Luis II Port of Entry, Avenue E and County 25th Street Preliminary Engineering New Construction $20,127
ARIZONA PHOENIX, AZ Pre-Engineer/Design and construct mill and replace - pavement resurfacing Other $12,918
ARIZONA YUMA (CA) Construction of an interpretative plaza, complete with retaining walls New Construction $750,000
ARIZONA Cold in place recycle; reconstruction Other $20,000
ARKANSAS PROVIDE GRADING AND STRUCTURES FOR 9.89 MILES OF A 4-LANE DIVIDED FACILITY ON NEW LOCATION New Construction $21,094,279
ARKANSAS CONTINUE MODIFICATION OF EXISTING INTERCHANGE Bridge Improvement $15,991,380
ARKANSAS ACHM REHABILITATION OF 4.30 MILES Pavement Improvement $1,663,847
ARKANSAS ACHM REHABILITATION OF 1.36 MILES Pavement Improvement $438,262