Add Cost per Area to Construction
This measure will create life cycle cost objects associated with the selected construction. You can set a material and installation cost, demolition cost, and O&M costs. Optionally existing cost objects already associated with building can be deleted. This measure will not affect energy use of the building.
In addition to the inputs for the cost values, a number of other inputs are exposed to specify when the cost first occurs and at what frequency it occurs in the future. This measure is intended to be used as an 'Always Run' measure to apply costs to the baseline simulation before any design alternatives manipulate it.
For baseline costs, 'Years Until Costs Start' indicates the year that the capital costs first occur. For new construction this will be typically be 0 and 'Demolition Costs Occur During Initial Construction' will be 'false'. For a retrofit 'Years Until Costs Start' is between 0 and the 'Expected Life' of the object, while 'Demolition Costs Occur During Initial Construction' is true. O&M cost and frequency can be whatever is appropriate for the component.
construction
Choose a Construction to Add Costs to
Choice
true
false
remove_costs
Remove Existing Costs
Boolean
true
false
true
true
true
false
false
material_cost_ip
Material and Installation Costs for Construction per Area Used
Double
$/ft^2
true
false
0
demolition_cost_ip
Demolition Costs for Construction per Area Used
Double
$/ft^2
true
false
0
years_until_costs_start
Years Until Costs Start
Integer
whole years
true
false
0
demo_cost_initial_const
Demolition Costs Occur During Initial Construction
Boolean
true
false
false
true
true
false
false
expected_life
Expected Life
Integer
whole years
true
false
20
om_cost_ip
O & M Costs for Construction per Area Used
Double
$/ft^2
true
false
0
om_frequency
O & M Frequency
Integer
whole years
true
false
1
Economics.Life Cycle Cost Analysis
Measure Type
ModelMeasure
string
Measure Function
Measure
string
Requires EnergyPlus Results
false
boolean
Uses SketchUp API
false
boolean
LICENSE.md
md
license
BFFB1AA6
README.md
md
readme
E8C8B150
README.md.erb
erb
readmeerb
703C9964
OpenStudio
2.0.0
2.0.0
measure.rb
rb
script
C55F964C
0416_NetArea_b.osm
osm
test
3D3EE8E9
AddCostPerAreaToConstruction_Test.rb
rb
test
9DF2FFF9