Keyword | end (timesheet) |
Purpose | The expected end date for the task. This can only be used for duration based task. For effort based task remaining has to be used. |
|
Syntax | end <date> |
|
Arguments | date | See date for details. |
Context | newtask, task (timesheet) |
task t2 "Task 2" { task t3 "Task 3" { duration 10d allocate r2 } } timesheet r2 2009-11-30 +1w { task t2.t3 { work 5d end 2009-12-10 status red "I need more time" { summary "This takes longer than expected" details -8<- To finish on time, I need help. Get this r1 guy to help me out here. * I want to have fun too! ->8- } } status yellow "My wife got ill" { summary "I might have to work from home for a few days next week." } }