The TaskJuggler User Manual

Project Management beyond Gantt Chart Drawing


<< end (report) << Table Of Contents >> endcredit >>


Keyword end (timesheet)

Purpose
The expected end date for the task. This can only be used for duration based task. For effort based task remaining has to be used.
Syntax end <date>
Arguments date
See date for details.
Context newtask, task (timesheet)

task t2 "Task 2" {
  task t3 "Task 3" {
    duration 10d
    allocate r2
  }
}

timesheet r2 2009-11-30 +1w {
  task t2.t3 {
    work 5d
    end 2009-12-10
    status red "I need more time" {
      summary "This takes longer than expected"
      details -8<-
        To finish on time, I need help. Get this r1 guy to help me out
        here.
        * I want to have fun too!
      ->8-
    }
  }
  status yellow "My wife got ill" {
    summary "I might have to work from home for a few days next week."
  }
}


<< end (report) << Table Of Contents >> endcredit >>