project prj "Project" "1.0" 2000-01-01 - 2000-03-01 { timingresolution 15min timezone "America/Denver" } resource tuxus "Tuxus" resource truck "Truck" { # Truck does not do any work! efficiency 0.0 } task t "Ship stones to customers" { start 2000-01-01 effort 5d # We need the truck to deliver the stones, so only allocate # tuxus when the truck is available. allocate tuxus allocate truck { mandatory } }