project "Test" 2009-02-04 - 2009-06-01 { timezone "Europe/Amsterdam" } include "checks.tji" resource r1 "Resource 1" resource r2 "Resource 2" resource r3 "Resource 3" resource r4 "Resource 4" task ms1 "Milestone 1" { ${FixStart "${projectstart}"} milestone } task ms2 "Milestone 2" { milestone scheduling alap ${FixEnd "${projectend}"} } task p1 "Parent Tasks" { task only_s_e "Only start or end dates" { task t1 "Task 1" { ${FixMS "${projectstart}"} } task t2 "Task 2" { start 2009-02-06 # This is an implicit milestone ${FixTask "2009-02-06" "2009-02-06"} } task t3 "Task 3" { end 2009-03-01 # This is an implicit milestone ${FixMS "2009-03-01"} } } task ms "Milestones" { task t1 "Task 1" { milestone ${FixMS "${projectstart}"} } task t2 "Task 2" { milestone scheduling alap ${FixMS "${projectend}"} } task t3 "Task 3" { start 2009-02-06 milestone ${FixMS "2009-02-06"} } task t4 "Task 4" { end 2009-03-01 milestone ${FixMS "2009-03-01"} } task t5 "Task 5" { start 2009-02-06 depends ms1 ${FixMS "2009-02-06"} } task t6 "Task 6" { end 2009-03-01 precedes ms2 ${FixMS "2009-03-01"} } } task w_effort "With effort" { task t1 "Task 1" { allocate r1 effort 20d scheduling asap ${FixTask "2009-02-04-09:00" "2009-03-03-17:00"} } task t2 "Task 2" { start 2009-02-06 effort 20d scheduling asap allocate r2 ${FixTask "2009-02-06-09:00" "2009-03-05-17:00"} } task t3 "Task 3" { effort 20d allocate r3 scheduling alap ${FixTask "2009-05-04-09:00" "2009-05-29-17:00"} } task t4 "Task 4" { end 2009-05-01 scheduling alap effort 20d allocate r4 ${FixTask "2009-04-03-09:00" "2009-04-30-17:00"} } } } task p2 "Parent Tasks 2" { task t1 "Task1" { ${FixMS "${projectstart}"} } task t2 "Task2" { depends !t1 ${FixMS "${projectstart}"} } task t3 "Task3" { scheduling alap ${FixMS "${projectend}"} } task t4 "Task4" { precedes !t3 ${FixMS "${projectend}"} } } taskreport inherit "InheritStartEnd" { formats html columns name, id, start, end, chart }