Road and bridge projects are expected to make up one of the biggest chunks of the jobs created in the stimulus package. Below, you’ll find a chart of more than 5,800 projects that have been approved by the U.S. Department of Transportation. Once given the green light, states can put the projects out to bid, contract them and begin construction work. So far, about 2,300 projects are under way.
Help us find out how much progress has been made on these projects by participating in our Stimulus Spot Check.
For more on the stimulus, check out our blog and resource page.
State | Urban Area | Project Description | Improvement Type | ARRA Funds Obligated |
---|---|---|---|---|
KANSAS | KANSAS CITY (MO) | US-69 CORRIDOR: FROM I-435 N TO .5 KM N OF 95TH ST IN OVERLAND PARK | Pavement Widening | $31,966,459 |
KANSAS | KANSAS CITY (MO) | US-69 CORRIDOR: FROM .5 KM N OF 95TH ST N TO I-35 & I-35 N TO 75TH ST IN OVERLAND PARK/ LENEXA | Pavement Widening | $51,977,796 |
KANSAS | CORR: K-61 FROM RN-MP CO LN NE TO APPX .2 MI NE OF CHISOLM RD | Pavement Widening | $36,046,133 | |
KANSAS | CORR: K-61 FROM APPX .2 MI NE OF CHISOLM RD NE TO 4-LN | Pavement Widening | $36,839,656 | |
KANSAS | KANSAS CITY (MO) | KANSAS CITY METROPOLITAN AREA - JOHNSON & WYANDOTTE COUNTIES | Other | $1,000,000 |
KANSAS | KANSAS CITY (MO) | COLLEGE BLVD FROM PFLUMM RD TO US-69 IN OVERLAND PARK | Pavement Widening | $1,000,000 |
KANSAS | WICHITA | ANDOVER RD FROM HARRY ST TO 1100' S OF US-54 IN ANDOVER | Pavement Widening | $1,234,800 |
KANSAS | WICHITA | BROADWAY BR OVER CHISHOLM CR IN PARK CITY | Other | $63,000 |
KANSAS | WICHITA | W GRAND AVE FROM MERIDIAN AVE TO N MAIN ST IN HAYSVILLE | Other | $18,000 |
KANSAS | LAWRENCE | INTERSECTION @ N 2ND ST & LOCUST ST IN LAWRENCE | Safety/Traffic Management | $2,000,000 |
KANSAS | KANSAS CITY (MO) | TONGANOXIE: US-24 @ NORTHSTAR DR | Pavement Improvement | $23,800 |
KANSAS | 4TH AVE (RS-809) FROM US-75 TO WOOD ST IN CANEY | Pavement Improvement | $177,500 | |
KANSAS | NATIONAL ST FROM LINKER ST TO WALL ST IN FORT SCOTT | Pavement Improvement | $228,180 | |
KANSAS | 8TH ST FROM N CITY LIMITS TO MAIN ST IN OSAWATOMIE | Pavement Improvement | $118,380 | |
KANSAS | BROADWAY ST FROM CENTENNIAL TO WILLIAMS IN PITTSBURG | Pavement Improvement | $265,500 | |
KENTUCKY | JACKSON-CAMPTON: FROM 0.43 M N OF KY 15 AT JACKSON TO 0.31 M S OF STILL HOUSE HOLLOW. (G&D) | Pavement Improvement | $21,960,000 | |
KENTUCKY | PROVIDE LEFT TURN LANE ON KY-15 @ WEST END OF WHITESBURG BYPASS. | Safety/Traffic Management | $1,589,000 | |
KENTUCKY | TOMPKINSVILLE - KY-90 (PRIORITY SECTION 1): FROM 0.34MI SOUTH OF BUSHONG ROAD EXTENDING NORTHERLY TO 0.68MI SOUTH OF CYCLONE ROAD (GRADE DRAIN & INC. SURFACE). (02CCR)(2002BOP)(SEE 3-276.11 FOR 2005HP | Pavement Improvement | $9,590,000 | |
KENTUCKY | REPAIR AND GRIND PAVEMENT ON I-24 EB & WB FROM 0.5 MILE E KY-293 (MP 45.133) IN LYON COUNTY TO KY-139 (MP 65.300) IN CALDWELL COUNTY. | Pavement Improvement | $12,226,812 | |
KENTUCKY | CINCINNATI (OH) | PARIS-COVINGTON RD; RECONSTRUCT FROM SOUTH OF KY-154 TO CAMPBELL COUNTY PARK. | Pavement Widening | $29,120,000 |
KENTUCKY | CINCINNATI (OH) | RECONSTRUCT 12TH ST. FR I-75 TO SCOTT STREET (OKI T.I.P.) | Pavement Improvement | $8,761,860 |
KENTUCKY | 12th St (KY 1120) in Covington from Russell St to Scott Street. Grade, Drain, and Surface for Roadway Reconstruction. | Pavement Improvement | $1,000,000 | |
KENTUCKY | REHABILITATE I-65, REPAIR AND GRIND PAVEMENT FROM MP 128.13 (FERN VALLEY ROAD) TO MP 131.89. | Pavement Improvement | $18,000,000 | |
KENTUCKY | US 68/KY 80; LAND BETWEEN THE LAKES. CONVERT DESIGN/BUILD COSTS TO FEDERAL FUNDS | Pavement Widening | $30,000,000 | |
KENTUCKY | BARDSTOWN-SPRINGFIELD; CONSTRUCT SPRINGFIELD NORTHWEST BYPASS. (02CCR)(06CCR) | New Construction | $15,938,900 | |
KENTUCKY | RECONSTRUCT US-150/STANFORD-MT. VERNON ROAD FROM CRAB ORCHARD TO BRODHEAD. (06CCN)(FUNDING SWAP WITH 8-163.10 AS SHOWN IN 2006SYP) | Pavement Improvement | $32,182,400 | |
KENTUCKY | MILL 1" THIN OVERLAY ON I-264 EB & WB FROM MP 22.61 TO I-71 (MP 22.97). | Pavement Improvement | $306,623 | |
KENTUCKY | SOUTH STREETS AVENUE SIDEWALK PROJECT- REPLACEMENT OF OLD, DETERIORATING SIDEWALKS AND EXPANSION OF THE CURRENT SIDEWALK SYSTEM. CURB AND GUTTER WILL BE ADDED. BEAUTIFICATION PROJECTS WILL ALSO BE | Pavement Improvement | $196,000 | |
KENTUCKY | POLK STREET EXTENSION PROJECT - PROJECT WILL ENABLE STUDENTS TO WALK OR BICYCLE TO 4 AREA SCHOOLS VIA SIDEWALK CONSTRUCTION,TRAFFIC CALMING MEASURES AND PEDESTRIAN AND BICYCLE CROSSING IMPROVEMENTS. | Transportation Enhancements | $247,000 | |
KENTUCKY | MORGANFIELD WALKING AND BICYCLE TRAIL - ADD BICYCLE RACKS AND SIGNAGE, DESIGNATION OF BICYCLE LANES CONSTRUCTION OF BICYCLE AND WALKING TRAIL SYSTEM AND AESTHETIC IMPROVEMENTS. | Transportation Enhancements | $55,500 | |
KENTUCKY | KY HISTORICAL SOCIETY HISTORIC MARKERS PHASE III - REPAIR OR REPLACEMENT OF DAMAGED HISTORICAL MARKERS. | Transportation Enhancements | $64,000 | |
KENTUCKY | EMINENCE PEDESTRIAN WALKWAY - REPLACEMENT OF DETERIORATED SIDEWALKS THROUGH DOWNTOWN EMINENCE. | Transportation Enhancements | $82,500 | |
KENTUCKY | US 31 W SIDEWALK PROJECT - INSTALLATION OF SIDEWALKS ALONG US 31 W. | Transportation Enhancements | $68,000 | |
KENTUCKY | PEDESTRIAN FACILITY PROJECT -REPLACEMENT OF AGING, CRACKED AND BUCKLED SIDEWALKS IN DOWNTOWN HARTFORD. | Transportation Enhancements | $120,000 | |
KENTUCKY | OLD CROFTON HOTEL BUILDING RESTORATION - RESTORE THE OLD CROFTON HOTEL, WHICH WILL SERVE AS A WELCOME CENTER. THIS HISTORIC STRUCTURE WAS BUILT IN 1904. | Other | $300,000 | |
KENTUCKY | CLINTON SIDEWALK REHAB & BEAUTIFICATION- REPLACE SIDEWALKS & IMPROVE LANDSCAPING ALONG NORTH WASHINGTON ST (US51) FROM CLAY ST TO NORTH ST, JEFFERSON ST FROM JACKSON ST TO CLAY ST, AND CLAY ST (KY123/ | Transportation Enhancements | $38,000 | |
KENTUCKY | PUBLIC SQUARE UNDERGROUND ELECTRICAL SERVICE - INSTALLATION OF UNDERGROUND ELECTRICAL SERVICE TO PROVIDE ENHANCED LIGHTING AND INSTALLATION OF BRICK PAVERS. | Transportation Enhancements | $12,500 | |
KENTUCKY | BARLOW SIDEWALK PROJECT - REPLACEMENT OF DETERIORATED SIDEWALKS. | Transportation Enhancements | $54,000 | |
KENTUCKY | PRESTONSBURG CONNECTIVITY PROJECT- DESIGN AND CONSTRUCTION OF A SIDEWALK TO CONNECT KY 1428 TO KY 321 NEAR THE ENTRANCE OF BIG SANDY COMMUNITY AND TECHNICAL COLLEGE. | Transportation Enhancements | $11,500 | |
KENTUCKY | CONSTRUCT NEW CONNECTOR FROM US-68/NORTHERN BYPASS TO INDUSTRIAL DRIVE IN LEBANON. (04CCR) | New Construction | $4,000,000 | |
KENTUCKY | EASTERN PARKWAY AT 3RD STREET - TRAFFIC AND PEDESTRIAN SAFETY IMPROVEMENTS ON EASTERN PARKWAY NEAR THIRD STREET. | Safety/Traffic Management | $1,600,000 | |
KENTUCKY | LEXINGTON-FAYETTE | BIG BARN TRANSPORTATION MUSEUM RESTORATION - STABILIZATION OF THE HISTORIC ÒBIG BARNÓ FOR THE CREATION OF A VISITOR CENTER AND CARRIAGE MUSEUM WITHIN THE STRUCTURE. | Transportation Enhancements | $964,000 |
KENTUCKY | WILKINSON BLVD. BIKE/PED FACILITIES - CREATION OF BICYCLE AND PEDESTRIAN FACILITIES ALONG THE KY RIVER AND WILKINSON BLVD FROM RIVERVIEW PARK TO FAIR OAKS LANE. | Pavement Improvement | $314,500 | |
KENTUCKY | GLASGOW OUTER LOOP FR US-68 TO THE LOUIE B. NUNN PARKWAY EAST OF GLASGOW. | New Construction | $17,200,000 | |
KENTUCKY | STREETSCAPE IMPROVEMENT PROJECT PHASE III - REPLACEMENT OF DETERIORATING SIDEWALKS AND INSTALLATION OF PEDESTRIAN CROSSWALKS, CURB RAMPS, DECORATIVE LIGHT FIXTURES AND BENCHES TO BEAUTIFY THE AREA. | Transportation Enhancements | $273,000 | |
KENTUCKY | RELOCATE US-60 BYPASS EAST OF OWENSBORO (EAST COUNTY CORRIDOR) PRIORITY SECTION: FROM REID ROAD EAST TO EXISTING US 60 EAST OF OWENSBORO. (98KYD)(2005HPP-KY158)(SEE 2-287.51 FOR FS"COMPONENT)" | Pavement Improvement | $27,200,000 | |
KENTUCKY | TATES CREEK TRAIL PROJECT- CONSTRUCT A SIDEWALK ALONG THE OLD ABANDONED RINEY B RAIL THAT RUNS ALONG KY 169. | Transportation Enhancements | $157,500 | |
KENTUCKY | HOSPITAL DRIVE SIDEWALK PROJECT - CONSTRUCTION OF 1700 LINEAR FEET OF SIDEWALK WITH CURB AND GUTTERING ALONG HOSPITAL DRIVE. THE NEW SIDEWALKS WILL CONNECT WITH US 60 SIDEWALKS. | Transportation Enhancements | $103,500 | |
KENTUCKY | US 431 BEAUTIFICATION PROJECT THIS PROJECT WILL MAKE AESTHETIC IMPROVEMENTS TO A ONE-MILE STRETCH OF US 431. ENHANCEMENTS WILL INCLUDE WELCOME SIGNS AND LANDSCAPING. | Transportation Enhancements | $24,000 | |
KENTUCKY | LOUISVILLE (IN) | KY-61 BEGINS SOUTH OF JOHN HARPER HIGHWAY (BROOKS ROAD) AND ENDS AT THE EXISTING 4-LANE SECTION SOUTH OF CARDINAL AVENUE. (2006BOPC) | Pavement Widening | $7,410,000 |
KENTUCKY | WIDENING OF KY-245 FROM KY-332 NORTH OF BARDSTOWN TO THE FLAGET HOSPITAL SITE. (2002BOPC) | Pavement Widening | $5,100,000 | |
KENTUCKY | US-27 TO I-75 (SECTION 4A SURFACING); FROM CORNBREAD BRANCH NEAR OLD JELLICO ROAD EAST TO BRIER CREEK BRIDGE. (2006BOPC) | Pavement Improvement | $6,020,000 | |
KENTUCKY | NEW CONNECTOR FROM KY-6 @ WOODBINE TO THE CORBIN BYPASS. (06CCR) | New Construction | $4,790,000 | |
KENTUCKY | REHAB PAVEMENT AND BRIDGE DECK ON US-127 BIG SUGAR CREEK BRIDGE (B08): REMOVE BRUSH BLOCK AND PLINTH WALLS AND PLACE A NEW DECK WITH BARRIER WALLS ON EXISTING BRIDGE DECK (2006BOPC) | Bridge Improvement | $268,968 | |
KENTUCKY | US25 @ KY1156 CONSTRUCT LEFT TURN LANES (B/C=2.1) (D-DISTRICT C-CONTRACTOR) (2002BOP) | Safety/Traffic Management | $910,000 | |
KENTUCKY | FRANKFORT-LEXINGTON US 421 LEESTOWN ROAD; WIDEN TO 5-LANES FR WEST OF US-60 TO 1600' EAST OF CHENAULT INDUSTRIAL ROAD. (SECTION 1) | Pavement Widening | $10,400,000 | |
KENTUCKY | GERMANTOWN STREETSCAPE PROJECT PHASE II - ONGOING STREETSCAPE PROJECT BY CONTINUING SIDEWALK REPLACEMENT ALONG KY 10. INCLUDING LANDSCAPING AND SCENIC BEAUTIFICATION. | Transportation Enhancements | $62,200 | |
KENTUCKY | PAVEMENT REHABILITATION ON THE WESTERN KENTUCKY PARKWAY. (BREAKOUT FROM 99-278.14) | Pavement Improvement | $1,100,000 | |
LOUISIANA | New Interstate Construction | New Construction | $9,000,000 | |
LOUISIANA | Bridge Replacement Project | Bridge Replacement | $1,737,971 | |
LOUISIANA | NEW ORLEANS | Intersection modification | Pavement Widening | $68,575,860 |
LOUISIANA | SHREVEPORT | New Interstate Construction | Pavement Improvement | $33,616,296 |
LOUISIANA | LAKE CHARLES | Pavement Rehabilitation | Pavement Improvement | $21,549,428 |
LOUISIANA | Landscaping, beautification project | Transportation Enhancements | $107,310 | |
LOUISIANA | Rehabilitation of two existing lanes on TIMED 4-lane project | Pavement Improvement | $2,744,414 | |
LOUISIANA | Bridge Replacement Project | Bridge Replacement | $571,465 | |
LOUISIANA | Rehabilitation of two existing lanes on TIMED 4-lane project | Pavement Improvement | $5,178,546 | |
LOUISIANA | Construction of a new vertical life bridge to replace a 55 yr. old pontoon bridge | Bridge Replacement | $32,878,408 | |
LOUISIANA | NEW ORLEANS | Reconstruction of existing roadway | Pavement Improvement | $12,010,598 |
LOUISIANA | Bridge Replacement Project | Bridge Replacement | $517,173 | |
LOUISIANA | Bridge Replacement Project | Bridge Replacement | $342,619 | |
LOUISIANA | NEW ORLEANS | Bicycle and Pedestrian Paths | Transportation Enhancements | $869,940 |
LOUISIANA | Construction of sidewalks along side of travel lanes of bridge | Bridge Replacement | $2,526,798 | |
LOUISIANA | SLIDELL | Intersection improvements, turn lanes, ramp widening | Pavement Improvement | $5,831,124 |
LOUISIANA | SLIDELL | Intersection improvements, turn lanes, ramp widening | Pavement Improvement | $1,848,392 |
LOUISIANA | MANDEVILLE-COVINGTON | Intersection improvements, turn lanes, ramp widening | Pavement Improvement | $5,852,429 |
LOUISIANA | Bridge Replacement Project | Bridge Replacement | $1,049,379 | |
LOUISIANA | Bridge Replacement Project | Bridge Replacement | $473,481 | |
LOUISIANA | Bridge Replacement Project | Bridge Replacement | $628,958 | |
LOUISIANA | Bridge Replacement Project | Bridge Replacement | $508,305 | |
LOUISIANA | NEW ORLEANS | Reconstruction of existing roadway | Pavement Improvement | $9,612,000 |
LOUISIANA | Bridge Replacement Project | Bridge Replacement | $412,700 | |
LOUISIANA | Bridge Replacement Project | Bridge Replacement | $481,159 | |
LOUISIANA | ALEXANDRIA | Reconstruction of two-lane roadway and new bridge to be constructed. | Pavement Improvement | $9,098,200 |
LOUISIANA | NEW ORLEANS | Construction of sidewalks, shared use bike lanes, dedicated use bike lanes, landscaping (trees), stiping, symbols, signs | Transportation Enhancements | $112,059 |
LOUISIANA | NEW ORLEANS | Construction of sidewalks, shared use bike lanes, dedicated use bike lanes, landscaping (trees), stiping, symbols, signs | Transportation Enhancements | $1,165,067 |
LOUISIANA | NEW ORLEANS | Construction of sidewalks, shared use bike lanes, dedicated use bike lanes, landscaping (trees), stiping, symbols, signs | Transportation Enhancements | $1,178,816 |
LOUISIANA | NEW ORLEANS | Construction of sidewalks, shared use bike lanes, dedicated use bike lanes, landscaping (trees), stiping, symbols, signs | Transportation Enhancements | $1,196,976 |
LOUISIANA | NEW ORLEANS | Construction of sidewalks, shared use bike lanes, dedicated use bike lanes, landscaping (trees), stiping, symbols, signs | Transportation Enhancements | $998,661 |
LOUISIANA | NEW ORLEANS | Construction of sidewalks, shared use bike lanes, dedicated use bike lanes, landscaping (trees), stiping, symbols, signs | Transportation Enhancements | $1,982,061 |
LOUISIANA | NEW ORLEANS | Construction of sidewalks | Transportation Enhancements | $963,914 |
LOUISIANA | NEW ORLEANS | Construction of sidewalks, shared use bike lanes, dedicated use bike lanes, landscaping (trees), stiping, symbols, signs | Transportation Enhancements | $476,905 |
LOUISIANA | NEW ORLEANS | Construction of sidewalks, shared use bike lanes, dedicated use bike lanes, landscaping (trees), stiping, symbols, signs | Transportation Enhancements | $32,628 |
LOUISIANA | NEW ORLEANS | Construction of sidewalks, shared use bike lanes, dedicated use bike lanes, landscaping (trees), stiping, symbols, signs | Transportation Enhancements | $1,015,893 |
LOUISIANA | NEW ORLEANS | Construction of sidewalks, shared use bike lanes, dedicated use bike lanes, landscaping (trees), stiping, symbols, signs | Transportation Enhancements | $16,837 |
LOUISIANA | NEW ORLEANS | Construction of sidewalks, shared use bike lanes, dedicated use bike lanes, landscaping (trees), stiping, symbols, signs | Transportation Enhancements | $21,377 |
LOUISIANA | NEW ORLEANS | Construction of sidewalks, shared use bike lanes, dedicated use bike lanes, landscaping (trees), stiping, symbols, signs | Transportation Enhancements | $1,575,665 |
LOUISIANA | NEW ORLEANS | Construction of sidewalks, shared use bike lanes, dedicated use bike lanes, landscaping (trees), stiping, symbols, signs | Transportation Enhancements | $9,100 |
LOUISIANA | Construction of four kiosks in Vivian, Plain Dealing, Sarepta, and Homer | Transportation Enhancements | $201,104 | |
MAINE | Highway Reconstruction: Beginning 0.33 of a mile northerly of Route 196 and extending northeasterly 6.75 miles to the Maine Turnpike Overpass. | Pavement Improvement | $12,838,260 | |
MAINE | Bridge Replacement: Veranda Street Overpass Bridge (#5052) over Canadian Railroad, located 0.30 of a mile northerly of Washington Street. | Bridge Improvement | $1,473,064 | |
MAINE | Highway Reconstruction: Beginning at the Rabbit Road and extending southeasterly 2.67 miles to 0.15 of a mile northerly of the Old Bangor Road. | Pavement Improvement | $7,883,762 | |
MAINE | PORTLAND | Bicycle/Pedestrian Facility Improvement: This project will design an extension of the Portland Trails system through the Bayside area of Portland along the abandoned Union Branch Rail Line extending | Transportation Enhancements | $800,000 |
MAINE | Bridge Replacement: Knights Hill Bridge(# 3194) over Meservy Brook and located 0.17 of a mile northerly of Route 173. | Bridge Improvement | $265,000 | |
MAINE | Intersection Improvement with a signal: Located at the intersection of Center Street, Joline Street, and Stetson Street. | Safety/Traffic Management | $532,135 | |
MAINE | Highway Reconstruction: Beginning at Route 4 and extending northerly 2.39 miles to Upper Street. | Pavement Improvement | $3,665,356 | |
MAINE | Highway Reconstruction: Beginning at Center Street and extending westerly 0.18 of a mile to Turner Street. | Pavement Improvement | $379,538 | |
MAINE | Highway reconstruction: Beginning at the convergence of the ramps to Main Street, extending 0.51 miles easterly to Robinson Gardens. Project will include construction of left-turn storage lanes at cer | Pavement Improvement | $2,106,788 | |
MAINE | Highway Resurfacing: Beginning at Main Street (Route 9) and extending westerly 0.97 of a mile to 0.10 of a mile easterly of Marshall Avenue. | Pavement Improvement | $583,689 | |
MAINE | Highway Resurfacing: Beginning at Parkside and extending 0.95 of a mile to Alfred Street. | Pavement Improvement | $429,554 | |
MAINE | Intersection Improvement with signal: Located at the intersection of Auburn Street and Lyseth Moore Drive. | Safety/Traffic Management | $224,761 | |
MAINE | Highway Improvements: Beginning 0.03 of a mile northerly of Park Street and extending 1.00 miles to 0.34 of a mile southerly of Hillview Avenue. | Pavement Improvement | $238,464 | |
MAINE | Eastern Trail, Bike/Pedestrian trail from Rt. 111 in Biddeford to Route 35 in Kennebunk. | Transportation Enhancements | $1,075,563 | |
MAINE | Highway Resurfacing: Beginning at Franklin Arterial and extending 0.29 of a mile to Elm Street. | Pavement Improvement | $170,419 | |
MAINE | Highway Resurfacing: Beginning at Saco Street and extending 0.88 of a mile to Spring Street. Includes shoulder resurfacing. | Pavement Improvement | $512,908 | |
MAINE | Highway Resurfacing: Beginning at North Street and extending 1.11 miles to Pine Ridge Road. | Pavement Improvement | $264,904 | |
MAINE | Highway Resurfacing: Beginning at the Westbrook town line and extending 0.74 of a mile to the Leighton Road. The project will include drainage and the installation of curbing. | Pavement Improvement | $461,242 | |
MAINE | Highway Resurfacing: Beginning at the Westbrook town line and extending 0.89 miles to Congress Street. Project includes alteration of 24 catch basins and replacement of approximately 1,000 feet of bi | Pavement Improvement | $293,979 | |
MAINE | Highway Reconstruction: Beginning at southerly end of Exit 28 Off-ramp and extending northerly 23.88 miles to the Maine Turnpike toll booth. Rehabilitation includes concrete rubblization, new pavement | Pavement Improvement | $35,500,000 | |
MAINE | Other Highway Maintenance: Topsham to Gardiner, I-295 NB, design cross overs to maintain traffic for mainline work for PIN 15114.50; one crossover in Topsham & one in Gardiner. | Safety/Traffic Management | $1,682,707 | |
MAINE | Steel Culvert Bridge Replacement: Salt Bay Bridge (#5974) over Salt Bay, located on the Damariscotta-Nobleboro town line. | Bridge Replacement | $439,459 | |
MAINE | Bridge Rehabilitation: Bridge Superstructure Replacement-Second Street Bridge (#0565) over Maine Central Railroad, located 0.71 of a mile northerly of Wilson Lane. | Bridge Replacement | $1,032,549 | |
MAINE | Bridge Deck Replacement: Lincoln Spur Bridge (#6074), located over Interstate 95, northbound and southbound. | Bridge Improvement | $1,349,425 | |
MAINE | Intersection Improvements without signal: Bypass lane construction located at the intersection of Route 1 and the Ashville Road. | Safety/Traffic Management | $226,133 | |
MAINE | Highway Resurfacing: Beginning 0.82 of a mile north of Christian Hill Road and extending northerly 1.66 miles to 0.12 of a mile south of West Lovell Road. | Pavement Improvement | $339,759 | |
MAINE | Highway Resurfacing: Beginning at Shore Road and extending northerly 0.90 miles to 0.17 of a mile northerly of Woodland Road. | Pavement Improvement | $285,272 | |
MAINE | Highway Resurfacing: Beginning 0.16 of a mile north of Route 35 and extending northerly 6.50 miles to 0.94 of a mile south of the Standish-Sebago town line. | Pavement Improvement | $1,163,709 | |
MAINE | Highway Resurfacing: Beginning at Route 11 and extending northerly 1.16 miles. | Pavement Improvement | $368,114 | |
MAINE | Highway Resurfacing: Beginning at Route 201 and extending northerly 0.65 of a mile to 0.19 of a mile northerly of Pishon Ferry Road. | Pavement Improvement | $102,978 | |
MAINE | Highway Resurfacing: Beginning 0.03 of a mile northerly of Greeley Street and extending northerly 0.85 of a mile to 0.30 of a mile northerly of Municipal Drive. | Pavement Improvement | $173,248 | |
MAINE | Highway Resurfacing: Beginning at Oak Street and extending easterly 0.37 of a mile to Route 11. | Pavement Improvement | $98,187 | |
MAINE | Highway Resurfacing: Beginning 0.05 of a mile westerly of the Chelsea-Randolph town line and extending easterly 3.67 miles to 0.10 of a mile easterly of the Augusta-Chelsea town line. | Pavement Improvement | $601,652 | |
MAINE | Highway Resurfacing: Beginning at Main Street and extending easterly 0.46 of a mile to College Avenue. | Pavement Improvement | $108,519 | |
MAINE | Highway Resurfacing: Beginning 0.03 of a mile south of Route 16 and extending northerly 1.26 miles. | Pavement Improvement | $272,734 | |
MAINE | Highway Resurfacing: Beginning 2.19 miles westerly of the Long Pond Twp town line and extending easterly 2.19 miles. | Pavement Improvement | $397,790 | |
MAINE | Highway Resurfacing: Beginning 0.05 of a mile westerly of the Sapling Township-Big Moose Township town line and extending easterly 6.10 miles to 0.46 of a mile westerly of Ski Resort Road. | Pavement Improvement | $917,345 | |
MAINE | Highway Resurfacing: Beginning at Somerset Avenue and extending northerly 6.27 miles to 0.03 of a mile northerly of Ford Hill Road. | Pavement Improvement | $1,134,140 | |
MAINE | Highway Resurfacing: Beginning 0.29 of a mile southerly of the Hamlin town line and extending northerly 5.69 miles to 1.18 miles southerly of Albert Cyr Road. | Pavement Improvement | $1,585,264 | |
MAINE | Highway Resurfacing: Beginning at Center Street and extending northerly 1.08 miles to 0.30 of a mile southerly of Mount Auburn Avenue. | Pavement Improvement | $381,206 | |
MAINE | Highway Resurfacing: Beginning at Cobbossee Avenue and extending easterly 1.10 miles to Route 201. | Pavement Improvement | $303,254 | |
MAINE | Highway Resurfacing: Beginning 0.17 of a mile westerly of the Huntington Hill Road and extending easterly 3.99 miles to 0.06 of a mile westerly of the Bog Hill Road. | Pavement Improvement | $714,526 | |
MAINE | Highway Resurfacing: Beginning at Route 23 and extending northerly 4.46 miles to 0.01 of a mile northerly of Winter Street. | Pavement Improvement | $952,097 | |
MAINE | Highway Resurfacing: Beginning 0.42 of a mile westerly of the I-95 Exit 102 On-ramp and extending easterly 1.69 miles to 0.11 of a mile westerly of the West Gardiner-Gardiner town line. | Pavement Improvement | $710,244 | |
MAINE | Highway Resurfacing: Beginning 1.87 miles west of Routes 104/139 and extending westerly 4.75 miles to 0.16 of a mile west of Bigelow Hill Road. | Pavement Improvement | $1,006,211 | |
MAINE | Highway Resurfacing: Beginning 0.38 of a mile southerly of York Hill Road and extending northerly 2.65 miles to Route 2. | Pavement Improvement | $606,208 | |
MAINE | Highway Resurfacing: Beginning at the Interstate 95 southbound Exit 185 ramps and extending northerly 0.65 of a mile to Grandview Avenue. | Pavement Improvement | $185,817 | |
MAINE | Highway Resurfacing: Beginning 0.10 miles southerly of the intersection of Mt. Hope and extending northerly 0.76 miles to 0.17 of a mile north of the Sylvan Road. | Pavement Improvement | $467,598 | |
MAINE | Highway Resurfacing: Beginning 0.37 of a mile northerly of Chase Mills Road and extending northerly 1.00 mile to 0.47 of a mile northerly of the Whiting town line. | Pavement Improvement | $265,079 | |
MAINE | Highway Resurfacing: Beginning at North Main Street and extending northerly 0.19 of a mile to Somerset Avenue. | Pavement Improvement | $47,567 | |
MAINE | Highway Resurfacing: Beginning at Minot Avenue and extending northerly 0.68 of a mile to Lisbon Street. | Pavement Improvement | $279,516 | |
MAINE | Highway Resurfacing: Beginning at High Street and extending northerly 0.51 of a mile to Court Street. | Pavement Improvement | $204,503 | |
MAINE | Culvert Repair: Culvert replacement, located near Exit #22. | Bridge Improvement | $275,000 | |
MAINE | Highway Resurfacing: Beginning at Warren Avenue and extending northerly 1.15 miles to Castine Avenue. | Pavement Improvement | $653,796 | |
MAINE | Highway Resurfacing: Beginning 0.13 of a mile north of the Washington Avenue Southbound on-ramp and extending southerly 0.42 of a mile. | Pavement Improvement | $225,915 | |
MAINE | Highway Resurfacing: Beginning 0.08 of a mile northerly of Eddy Road and extending northerly 1.02 miles to 0.05 of a mile northerly of Cochran Road. | Pavement Improvement | $512,452 | |
MAINE | Highway Resurfacing: Beginning 3.74 miles southerly of the The Forks Plantation town line and extending northerly 3.77 miles. | Pavement Improvement | $787,207 | |
MAINE | Curb to Curb Mill & Fill 1 1/4 inch; 500 feet west of the bridge to Prescott Street; Route 2/4/27 intersection to Hill Street. Mill & Fill 1 1/4 inch; Hill Street to High Street; Prescott Street to 3 | Pavement Improvement | $422,428 | |
MAINE | Highway Resurfacing: Beginning 0.26 of a mile northerly of Sandy Stream Road and extending northerly 13.65 miles to 0.01 of a mile southerly of the Canadian border. | Pavement Improvement | $2,471,123 | |
MAINE | Highway Resurfacing: Beginning 0.16 of a mile southerly of the Parlin Pond Township town line and extending northerly 13.62 miles to 2.60 miles northerly of the Parlin Pond Township-Jackman town line | Pavement Improvement | $2,504,120 | |
MAINE | Highway Resurfacing: Beginning 325' easterly of the I-95 northbound Exit 185 ramps and extending northerly 0.23 of a mile to the I-95 southbound Exit 185 ramps. | Pavement Improvement | $89,609 | |
MAINE | Highway Resurfacing: Beginning at Western Avenue and extending northerly 4.02 miles to the Interstate 395 Exit 2 eastbound ramps. | Pavement Improvement | $1,262,169 | |
MAINE | Highway Resurfacing: Beginning at the Mattamiscontis TWP town line and extending southerly 10.37 miles to 0.55 of a mile southerly of the Exit 217 on-ramp. | Pavement Improvement | $4,007,667 | |
MAINE | Highway Resurfacing: Beginning at the T2 R8 NWP town line and extending southerly 7.06 miles to the Mattamiscontis TWP town line. | Pavement Improvement | $2,608,467 | |
MAINE | Bridge Substructure Rehabilitation: Sedgwick Bridge (#3257) over Eggemoggin Reach, located on the Deer Isle-Sedgwick town line. | Bridge Improvement | $8,571,897 | |
MAINE | Replacement of Spruce Head Bridge (5578) over Atlantic Ocean, located 0.65 of a mile southerly of Route 73. | Bridge Replacement | $2,906,091 | |
MAINE | Highway Resurfacing: Beginning 0.55 of a mile southerly of the Exit 217 On-ramp and extending southerly 15.60 miles to the Alton/Old Town town line. | Pavement Improvement | $4,513,577 | |
MAINE | Highway Resurfacing: Beginning at the T2 R9 NWP town line and extending southerly 8.22 miles to the T2 R8 NWP town line. | Pavement Improvement | $2,542,725 | |
MAINE | Highway Resurfacing: Beginning at the intersection of Route 1 and extending easterly approximately 6.7 miles. | Pavement Improvement | $3,397,597 | |
MAINE | Capital retrofits and infrastructure improvements that enhance quality treatment of stormwater runoff in an urban impaired stream watershed as recommended by the Long Creek Watershed Planning Initiati | Other | $2,046,998 | |
MAINE | Dover-Foxcroft, State Route 15, Highway Improvements | Pavement Improvement | $2,851,000 | |
MARYLAND | Resurfacing | Pavement Improvement | $4,657,659 | |
MARYLAND | Resurfacing | Pavement Improvement | $4,612,059 | |
MARYLAND | Resurfacing | Pavement Improvement | $4,623,563 | |
MARYLAND | Resurfacing | Pavement Improvement | $4,616,619 | |
MARYLAND | Resurfacing | Pavement Improvement | $4,828,636 | |
MARYLAND | Signalization | Safety/Traffic Management | $5,287,442 | |
MARYLAND | Resurfacing | Pavement Improvement | $2,299,728 | |
MARYLAND | Resurfacing | Pavement Improvement | $2,314,963 | |
MARYLAND | Resurfacing | Pavement Improvement | $2,309,460 | |
MARYLAND | Resurfacing | Pavement Improvement | $2,288,732 | |
MARYLAND | Lighting | Safety/Traffic Management | $11,093,131 | |
MARYLAND | Sidewalks | Pavement Improvement | $2,377,547 | |
MARYLAND | Sidewalks | Pavement Improvement | $3,612,818 | |
MARYLAND | Sidewalks | Pavement Improvement | $2,302,300 | |
MARYLAND | Sidewalks | Pavement Improvement | $2,936,648 | |
MARYLAND | Sidewalks | Pavement Improvement | $1,794,107 | |
MARYLAND | Resurfacing | Pavement Improvement | $2,205,364 | |
MARYLAND | Resurfacing | Pavement Improvement | $2,320,897 | |
MARYLAND | Resurfacing | Pavement Improvement | $2,291,662 | |
MARYLAND | Resurfacing | Pavement Improvement | $2,328,142 | |
MARYLAND | Guardrail | Safety/Traffic Management | $379,808 | |
MARYLAND | Guardrail | Safety/Traffic Management | $299,042 | |
MARYLAND | Guardrail | Safety/Traffic Management | $268,485 | |
MARYLAND | Guardrail | Safety/Traffic Management | $341,541 | |
MARYLAND | Guardrail | Safety/Traffic Management | $297,440 | |
MARYLAND | Guardrail | Safety/Traffic Management | $498,332 | |
MARYLAND | Resurfacing | Pavement Improvement | $2,297,378 | |
MARYLAND | Resurfacing | Pavement Improvement | $4,612,278 | |
MARYLAND | Resurfacing | Pavement Improvement | $4,612,522 | |
MARYLAND | Resurfacing | Pavement Improvement | $2,277,771 | |
MARYLAND | Resurfacing | Pavement Improvement | $4,592,808 | |
MARYLAND | Resurfacing | Pavement Improvement | $4,576,033 | |
MARYLAND | Resurfacing | Pavement Improvement | $5,152,037 | |
MARYLAND | Resurfacing | Pavement Improvement | $4,576,062 | |
MARYLAND | Resurfacing | Pavement Improvement | $4,576,062 | |
MARYLAND | Resurfacing | Pavement Improvement | $2,287,492 | |
MARYLAND | Resurfacing | Pavement Improvement | $4,592,808 | |
MARYLAND | Resurfacing | Pavement Improvement | $2,284,068 | |
MARYLAND | Resurfacing | Pavement Improvement | $4,591,671 | |
MARYLAND | Safety | Pavement Improvement | $1,344,595 | |
MARYLAND | Resurfacing | Pavement Improvement | $2,308,339 | |
MARYLAND | WASHINGTON (DC-MD-VA) | Clean/Paint Bridges | Bridge Improvement | $1,714,856 |
MARYLAND | WASHINGTON (DC-MD-VA) | Clean/Paint Bridges | Bridge Improvement | $2,130,066 |
MARYLAND | Guardrail | Safety/Traffic Management | $833,976 | |
MARYLAND | Guardrail | Safety/Traffic Management | $833,976 | |
MARYLAND | Guardrail | Safety/Traffic Management | $1,904,760 | |
MARYLAND | Guardrail | Safety/Traffic Management | $852,738 | |
MARYLAND | Signing | Safety/Traffic Management | $5,075,685 | |
MARYLAND | Guardrail | Safety/Traffic Management | $2,083,487 | |
MARYLAND | Guardrail | Safety/Traffic Management | $3,013,319 | |
MARYLAND | Signalization | Safety/Traffic Management | $1,824,752 | |
MARYLAND | Signing | Safety/Traffic Management | $3,672,297 | |
MARYLAND | Signalization | Safety/Traffic Management | $6,672,881 | |
MARYLAND | Signalization | Safety/Traffic Management | $1,939,995 | |
MARYLAND | Signing | Safety/Traffic Management | $6,495,427 | |
MARYLAND | DISTRICT 4 & 7 - VARIOUS LOCATIONS - WETLAND AND TREE PLANTINGS | Transportation Enhancements | $558,489 | |
MARYLAND | Signing | Safety/Traffic Management | $2,284,082 | |
MARYLAND | Landscaping | Transportation Enhancements | $280,400 | |
MARYLAND | Landscaping | Transportation Enhancements | $266,341 | |
MARYLAND | Landscaping | Transportation Enhancements | $334,101 | |
MARYLAND | FREDERICK | Landscaping | Transportation Enhancements | $543,309 |
MARYLAND | Safety and Resurfacing | Pavement Improvement | $3,695,543 | |
MARYLAND | Guardrail | Safety/Traffic Management | $1,471,190 | |
MARYLAND | Guardrail | Safety/Traffic Management | $7,049,583 | |
MARYLAND | Landscaping | Transportation Enhancements | $339,191 | |
MARYLAND | Safety and Resurfacing | Pavement Improvement | $3,642,258 | |
MARYLAND | Safety & Resurfacing | Pavement Improvement | $4,338,694 | |
MARYLAND | WASHINGTON (DC-MD-VA) | Landscaping | Transportation Enhancements | $542,560 |
MARYLAND | Landscaping | Transportation Enhancements | $676,104 | |
MARYLAND | Safety & Resurfacing | Pavement Improvement | $1,143,318 | |
MARYLAND | Resurfacing | Pavement Improvement | $2,602,428 | |
MARYLAND | Geometric Improvements | Pavement Improvement | $1,866,782 | |
MARYLAND | BALTIMORE,MD | Safety & Resurfacing | Pavement Improvement | $5,173,792 |
MARYLAND | WASHINGTON (DC-MD-VA) | Bridge Replacement | Bridge Replacement | $1,521,908 |
MARYLAND | BALTIMORE,MD | Rehabitation | Pavement Improvement | $7,082,521 |
MARYLAND | Ridesharing Facilities | Pavement Widening | $316,386 | |
MARYLAND | Landscaping | Transportation Enhancements | $111,097 | |
MARYLAND | Resurfacing | Pavement Improvement | $1,193,354 | |
MARYLAND | Safety & Resurfacing | Pavement Improvement | $3,206,058 | |
MARYLAND | Safety and Resurfacing | Pavement Improvement | $1,325,696 |
Source: FDIC