Road and bridge projects are expected to make up one of the biggest chunks of the jobs created in the stimulus package. Below, you’ll find a chart of more than 5,800 projects that have been approved by the U.S. Department of Transportation. Once given the green light, states can put the projects out to bid, contract them and begin construction work. So far, about 2,300 projects are under way.
Help us find out how much progress has been made on these projects by participating in our Stimulus Spot Check.
For more on the stimulus, check out our blog and resource page.
State | Urban Area | Project Description | Improvement Type | ARRA Funds Obligated |
---|---|---|---|---|
GEORGIA | SAVANNAH | This project is the milling and resurfacing of SR 30. This section of SR 30 needs resurfacing because the existing pavement is deteriorating. SR 30 was last resurfaced in 1975. | Pavement Improvement | $204,108 |
GEORGIA | This project is the milling and resurfacing of SR 32. This section of SR 32 needs resurfacing because the existing pavement is deteriorating. SR 32 was last resurfaced in 1998. | Pavement Improvement | $1,915,833 | |
GEORGIA | This project is the resurfacing of SR 4. This section of SR 4 needs resurfacing because the existing pavement is deteriorating. SR 4 was last resurfaced in 1998. | Pavement Improvement | $5,004,817 | |
GEORGIA | This project is the resurfacing of SR 40 connector. This section of SR 40 connector needs resurfacing because the existing pavement is deteriorating. SR 40 Connector was last resurfaced in 2000. | Pavement Improvement | $246,728 | |
GEORGIA | This project is the milling and resurfacing of SR 1 Businesss. This section of SR 1 Business needs resurfacing because the existing pavement is deteriorating. SR 1 Business was last resurfaced in 1997 | Pavement Improvement | $1,046,745 | |
GEORGIA | This project is the milling and resurfacing of SR 3. This section of SR 3 needs resurfacing because the existing pavement is deteriorating. SR 3 was last resurfaced in 1999. | Pavement Improvement | $1,574,895 | |
GEORGIA | ATLANTA | This project is the resurfacing on SR 140. This section of SR 140 needs resurfacing because the existing pavement is deteriorating. SR 140 was last resurfaced in 1990. | Pavement Improvement | $3,216,978 |
GEORGIA | This project is the milling and resurfacing of SR 27 West. This section of SR 27 West needs resurfacing because the existing pavement is deteriorating. SR 27 West was last resurfaced in 1998. | Pavement Improvement | $945,661 | |
GEORGIA | This project is the milling and resurfacing of SR 27. This section of SR 27 needs resurfacing because the existing pavement is deteriorating. SR 27 was last resurfaced in 1998. | Pavement Improvement | $1,002,998 | |
GEORGIA | AUGUSTA (SC) | This project is the milling and resurfacing of SR 28. This section of SR 28 needs resurfacing because the existing pavement is deteriorating. SR 28 was last resurfaced in 1995. | Pavement Improvement | $2,124,848 |
GEORGIA | This project is the milling and resurfacing of SR 117. This section of SR 117 needs resurfacing because the existing pavement is deteriorating. SR 117 was last resurfaced in 1989. | Pavement Improvement | $3,102,028 | |
GEORGIA | This project is the milling and resurfacing of SR 4. This section of SR 4 needs resurfacing because the existing pavement is deteriorating. SR 4 was last resurfaced in 2000. | Pavement Improvement | $3,593,850 | |
GEORGIA | ATLANTA | This project is the milling and resurfacing of SR 9. This section of SR 9 needs resurfacing because the existing pavement is deteriorating. SR 9 was last resurfaced in 2000. | Pavement Improvement | $560,224 |
GEORGIA | ATLANTA | This project is the milling and resurfacing of SR 3/US 19. This section of SR 3 needs resurfacing because the existing pavement is deteriorating. SR 3 was last resurfaced in 1987. | Pavement Improvement | $1,044,334 |
GEORGIA | ATLANTA | This project is the milling and resurfacing of SR 9. This section of SR 9 needs resurfacing because the existing pavement is deteriorating. SR 9 was last resurfaced in 2000. | Pavement Improvement | $2,612,378 |
GEORGIA | ATLANTA | This project is the milling and resurfacing of SR 10. This section of SR 10 needs resurfacing because the existing pavement is deteriorating. SR 10 was last resurfaced in 1990. | Pavement Improvement | $5,101,371 |
GEORGIA | ATLANTA | This project is the milling and resurfacing of SR 14 Spur. This section of SR 14 Spur needs resurfacing because the existing pavement is deteriorating. SR 14 Spur was last resurfaced in 1997. | Pavement Improvement | $1,045,509 |
GEORGIA | ATLANTA | This project is the resurfacing of SR 139. This section of SR 139 needs resurfacing because the existing pavement is deteriorating. SR 139 was last resurfaced in 1989. | Pavement Improvement | $677,413 |
GEORGIA | ATLANTA | This project is the milling and resurfacing of SR 54. This section of SR 54 needs resurfacing because the existing pavement is deteriorating. SR 54 was last resurfaced in 1994. | Pavement Improvement | $1,981,879 |
GEORGIA | ATLANTA | This project is the milling and resurfacing of SR 92. This section of SR 92 needs resurfacing because the existing pavement is deteriorating. SR 92 was last resurfaced in 2002. | Pavement Improvement | $2,791,017 |
GEORGIA | GAINESVILLE | This project is the resurfacing of SR 11. This section of SR 11 needs resurfacing because the existing pavement is deteriorating. SR 11 was last resurfaced in 1997. | Pavement Improvement | $1,776,000 |
GEORGIA | This project is the resurfacing of SR 53. This section of SR 53 needs resurfacing because the existing pavement is deteriorating. SR 53 was last resurfaced in 1998. | Pavement Improvement | $1,914,750 | |
GEORGIA | This project is the resurfacing of SR 384. This section of SR 384 needs resurfacing because the existing pavement is deteriorating. SR 384 was last resurfaced in 1999. | Pavement Improvement | $1,021,200 | |
GEORGIA | This project is the resurfacing of SR 51. This section of SR 51 needs resurfacing because the existing pavement is deteriorating. SR 51 was last resurfaced in 2001. | Pavement Improvement | $1,637,250 | |
GEORGIA | This project is the resurfacing of SR 356. This section of SR 356 needs resurfacing because the existing pavement is deteriorating. SR 356 was last resurfaced in 1985. | Pavement Improvement | $1,932,688 | |
GEORGIA | ATLANTA | This project is the milling and resurfacing of SR 9. This section of SR 9 needs resurfacing because the existing pavement is deteriorating. SR 9 was last resurfaced in 2004. | Pavement Improvement | $3,146,850 |
GEORGIA | This project is the resurfacing of SR 63. This section of SR 63 needs resurfacing because the existing pavement is deteriorating. SR 63 was last resurfaced in 1998. | Pavement Improvement | $2,021,050 | |
GEORGIA | This project is the resurfacing of SR 520. This section of SR 520 needs resurfacing because the existing pavement is deteriorating. SR 520 was last resurfaced in 1998. | Pavement Improvement | $1,451,691 | |
GEORGIA | ATLANTA | This project is the milling and resurfacing of I-575/SR 417. This section of SR 417 needs resurfacing because the existing pavement is deteriorating. SR 417 was last resurfaced in 1983. | Pavement Improvement | $30,718,936 |
GEORGIA | This project is the milling and resurfacing of SR 137. This section of SR 137 needs resurfacing because the existing pavement is deteriorating. SR 137 was last resurfaced in 1997. | Pavement Improvement | $1,803,431 | |
GEORGIA | This project is the milling and resurfacing of SR 7. This section of SR 7 needs resurfacing because the existing pavement is deteriorating. SR 7 was last resurfaced in 1999. | Pavement Improvement | $3,552,478 | |
GEORGIA | This project is the milling and resurfacing of SR 153. This section of SR 153 needs resurfacing because the existing pavement is deteriorating. SR 153 was last resurfaced in 1994. | Pavement Improvement | $1,727,731 | |
GEORGIA | ATLANTA | This project is the milling and resurfacing of SR 155. This section of SR 155 needs resurfacing because the existing pavement is deteriorating. SR 155 was last resurfaced in 1998. | Pavement Improvement | $3,405,522 |
GEORGIA | This project is the milling and resurfacing of SR 83. This section of SR 83 needs resurfacing because the existing pavement is deteriorating. SR 83 was last resurfaced in 1985. | Pavement Improvement | $2,775,106 | |
GEORGIA | AUGUSTA (SC) | This project is the milling and resurfacing of SR 4. This section of SR 4 needs resurfacing because the existing pavement is deteriorating. SR 4 was last resurfaced in 1992. | Pavement Improvement | $3,898,828 |
GEORGIA | This project is the milling and resurfacing of SR 16. This section of SR 16 needs resurfacing because the existing pavement is deteriorating. SR 16 was last resurfaced in 1984. | Pavement Improvement | $2,046,604 | |
GEORGIA | This project is the milling and resurfacing of SR 16. This section of SR 16 needs resurfacing because the existing pavement is deteriorating. SR 16 was last resurfaced in 1987. | Pavement Improvement | $2,297,111 | |
GEORGIA | This project is the milling and resurfacing of SR 4 Business.This section of SR 4 Business needs resurfacing because the existing pavement is deteriorating. SR 4 Business was last resurfaced in 1991. | Pavement Improvement | $1,980,285 | |
GEORGIA | This project is the resurfacing of SR 17. This section of SR 17 needs resurfacing because the existing pavement is deteriorating. SR 17 was last resurfaced in 1999. | Pavement Improvement | $1,057,018 | |
GEORGIA | This project is the resurfacing of SR 23. This section of SR 23 needs resurfacing because the existing pavement is deteriorating. SR 23 was last resurfaced in 1994. | Pavement Improvement | $4,881,333 | |
GEORGIA | This project is the resurfacing of SR 25. This section of SR 25 needs resurfacing because the existing pavement is deteriorating. SR 25 was last resurfaced in 1992. | Pavement Improvement | $2,029,302 | |
GEORGIA | ATLANTA | This project is the resurfacing of SR 20. This section of SR 20 needs resurfacing because the existing pavement is deteriorating. SR 20 was last resurfaced in 1990. | Pavement Improvement | $506,033 |
GEORGIA | ATLANTA | This project is the resurfacing of SR 20. This section of SR 20 needs resurfacing because the existing pavement is deteriorating. SR 20 was last resurfaced in 1990. | Pavement Improvement | $2,188,101 |
GEORGIA | ATLANTA | This project is the resurfacing of SR 236. This section of SR 236 needs resurfacing because the existing pavement is deteriorating. SR 236 was last resurfaced in 1988. | Pavement Improvement | $1,238,039 |
GEORGIA | ATLANTA | This project is the resurfacing of SR 360. This section of SR 360 needs resurfacing because the existing pavement is deteriorating. SR 360 was last resurfaced in 1984. | Pavement Improvement | $659,314 |
GEORGIA | This project is the resurfacing of SR 41. This section of SR 41 needs resurfacing because the existing pavement is deteriorating. SR 41 was last resurfaced in 1996. | Pavement Improvement | $2,106,854 | |
GEORGIA | This project is the resurfacing of SR 128. This section of SR 128 needs resurfacing because the existing pavement is deteriorating. SR 128 was last resurfaced in 1999. | Pavement Improvement | $2,208,045 | |
GEORGIA | This project is the resurfacing of SR 18. This section of SR 18 needs resurfacing because the existing pavement is deteriorating. SR 18 was last resurfaced in 1993. | Pavement Improvement | $3,130,217 | |
GEORGIA | This project is the resurfacing of SR 44. This section of SR 44 needs resurfacing because the existing pavement is deteriorating. SR 44 was last resurfaced in 1998. | Pavement Improvement | $6,056,772 | |
GEORGIA | This project is the resurfacing of SR 30/US 280. This section of SR 30 needs resurfacing because the existing pavement is deteriorating. SR 30 was last resurfaced in 1992. | Pavement Improvement | $2,813,411 | |
GEORGIA | This project is the resurfacing of SR 30. This section of SR 30 needs resurfacing because the existing pavement is deteriorating. SR 30 was last resurfaced in 1997. | Pavement Improvement | $3,236,978 | |
GEORGIA | This project is the resurfacing of SR 126. This section of SR 126 needs resurfacing because the existing pavement is deteriorating. SR 126 was last resurfaced in 1998. | Pavement Improvement | $2,003,639 | |
GEORGIA | This project is the resurfacing of SR 47. This section of SR 47 needs resurfacing because the existing pavement is deteriorating. SR 47 was last resurfaced in 1995. | Pavement Improvement | $3,282,708 | |
GEORGIA | GAINESVILLE | This project is the removal of selected concrete slabs on SR 365. The reason for removal and replacement of the selected concrete slabs is due deterioration. The last time any work was done on SR 365 | Pavement Improvement | $4,558,437 |
GEORGIA | WARNER ROBINS | This project is the resurfacing of SR 11 Business. This section of SR 11 Business needs resurfacing because the existing pavement is deteriorating. SR 11 Business was last resurfaced in 1994. | Pavement Improvement | $992,900 |
GEORGIA | This project is the resurfacing of SR 164. This section of SR 164 needs resurfacing because the existing pavement is deteriorating. SR 164 was last resurfaced in 1993. | Pavement Improvement | $1,232,100 | |
GUAM | Rte 2, Reconstruction or Repair of Three Culverts and One Slide | Other | $1,582,000 | |
GUAM | Rte 4 Widening and Resurfacing Ylig Bridge to Pago Bay | Other | $4,400,000 | |
GUAM | MassoRiver Bridge, Abutment Repair | Other | $220,000 | |
GUAM | Rte 17 Rehabilitation and Widening in several areas, Phase 1 | Other | $5,298,000 | |
GUAM | Rte 25 (Alageta Road) Reconstruction and Widening (Bello Road to Route 26) | Other | $6,500,000 | |
HAWAII | Limited to extending the life of the pavement by cold planing and resurfacing (1 1/2" maximum) areas that are starting to show pavement distress. Use of slurry seal, crack seals, white topping and/or | Pavement Improvement | $5,605,823 | |
HAWAII | INTERSTATE ROUTE H-1 AT FARRINGTON HIGHWAY, MAKAKILO SEPARATION & MILITARY ROAD OVERPASSES; PE, ROW & CON FOR SEISMIC RETROFIT | Bridge Improvement | $1,485,691 | |
HAWAII | HAWAII BELT ROAD, CLEAN AND PAINT STEEL MEMBERS, NINOLE, MAULUA, KUWAIKAHI, AND KUKAIAU BRIDGES (CON) | Bridge Improvement | $8,274,152 | |
HAWAII | HONOLULU | TRAFFIC SIGNALS AT VARIOUS LOCATIONS, PHASE 10 (P, C) | Safety/Traffic Management | $3,407,221 |
HAWAII | HANA HIGHWAY PAVEMENT PREVENTIVE MAINTENANCE, KAUPAKALUA ROAD TO HUELO (CON) | Pavement Improvement | $1,363,530 | |
HAWAII | Resurface and reconstruct damaged areas of the pavement. Safety (including guardrail and shoulder improvements) and ADA improvements could be included. | Pavement Improvement | $3,893,243 | |
HAWAII | Limited to extending the life of the pavement by cold planing and resurfacing (1 1/2" maximum) areas that are starting to show pavement distress. Use of slurry seal, crack seals, white topping and/or | Pavement Improvement | $1,904,805 | |
HAWAII | KUHIO HIGHWAY RESURFACING, KAWAIHAU ROAD TO KAPAA BRIDGE (CON) | Pavement Improvement | $1,021,416 | |
HAWAII | MAALO ROAD RESURFACING, MILE POST 0.0 TO MILE POST 1.0 | Pavement Improvement | $729,083 | |
HAWAII | HONOLULU | RT 83 KAMEHAMEHA HIGHWAY AT PUNALUU STREAM, PE/ROW/CON FOR BRIDGE REPLACEMENT | Bridge Replacement | $20,343,107 |
HAWAII | Reconstruction and beautification of Market Street from Kahawai Street to Makuhau Road. Install drainage system, street lights, landscaping and irrigation. | Pavement Improvement | $5,287,166 | |
IDAHO | Cement Recycled Asphalt Base Stabilization on 3.5 miles of road | Other | $81,000 | |
IDAHO | Replace one deficient, restricted-access bridge | New Bridge Construction | $36,976,832 | |
IDAHO | Widen 6.37 miles of congested rural road | Pavement Widening | $2,780,627 | |
IDAHO | Widen 1.71 miles of road | Pavement Widening | $5,403,562 | |
IDAHO | Add sidewalks and lighting along 0.454 miles of road | Other | $188,212 | |
IDAHO | POCATELLO | Widen 1.2 miles of congested urban Interstate | Pavement Improvement | $11,569,574 |
IDAHO | Construct 20.28 new lane-miles and one new bridge | New Construction | $42,354,235 | |
IDAHO | Widen 1.338 miles of road | Pavement Widening | $4,210,319 | |
IDAHO | IDAHO FALLS | Sealcoat local streets throughout Idaho Falls city | Pavement Improvement | $866,027 |
IDAHO | BOISE CITY | One mile of landscaping along the newly constructed Ten Mile interchange on I 84 | Other | $108,880 |
IDAHO | Widen 2.619 miles of road | Pavement Widening | $5,589,767 | |
IDAHO | Resurface 1.49 miles of road | Other | $66,000 | |
IDAHO | Resurface one intersection | Other | $81,000 | |
IDAHO | Resurface 0.45 mile of road | Other | $56,000 | |
IDAHO | Resurface 14.345 miles of road | Other | $65,000 | |
IDAHO | Resurface 1 mile of road | Other | $66,000 | |
IDAHO | Resurface 3.2 miles of road | Other | $56,000 | |
IDAHO | Resurface 0.722 mile of road | Other | $81,000 | |
IDAHO | Resurface 0.489 mile of road | Other | $78,500 | |
IDAHO | Cement Recycled Asphalt Base Stabilization on 1.48 miles of road | Other | $81,000 | |
IDAHO | Resurface 3 miles of road | Other | $80,000 | |
IDAHO | Resurface 4.2 miles of road | Other | $81,000 | |
IDAHO | Resurface 4.6 miles of road | Other | $66,000 | |
IDAHO | Cement Recycled Asphalt Base Stabilization on 1.5 miles of road | Other | $81,000 | |
IDAHO | Resurface 0.19 mile of road | Other | $66,000 | |
IDAHO | Resurface 0.61 mile of road | Other | $63,000 | |
IDAHO | POCATELLO | Resurface 1.232 mile of road | Other | $65,000 |
IDAHO | Resurface 0.426 mile of road | Other | $66,000 | |
IDAHO | Resurface 1.02 miles of road | Other | $81,000 | |
IDAHO | Resurface 0.192 mile of road | Other | $62,000 | |
IDAHO | Resurface 4.543 miles of road | Other | $56,000 | |
IDAHO | Resurface 2 miles of road | Other | $81,000 | |
IDAHO | Resurface 0.47 mile of road | Other | $66,000 | |
IDAHO | Resurface 0.46 mile of road | Other | $81,000 | |
IDAHO | Provide for curation and management of artifacts | Other | $162,960 | |
IDAHO | BOISE CITY | I 84, VISTA AVE IC, BOISE, BRIDGE #21590 - ARRA (construction) | Pavement Widening | $24,029,318 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | LAKE ST TO N OF I-290 (EISENHOWER EXPY) | Pavement Improvement | $1,538,505 |
ILLINOIS | ROCKFORD | E STATE ST TO MULBERRY ST IN ROCKFORD | Pavement Improvement | $518,841 |
ILLINOIS | ILL 82 IN GENESEO TO STATE ST; STATE STEER TO MUD CREEK IN ATKINSON | Pavement Improvement | $2,777,902 | |
ILLINOIS | US 20 / IL 26 - Resurfacing on US 20 north of Freeport from east and west of IL 26 and on IL 26 from sourth of Fairview Road to * | Pavement Improvement | $1,880,580 | |
ILLINOIS | Various Structures in Adams, Christian & Morgan Counties | Bridge Improvement | $220,000 | |
ILLINOIS | ROCKFORD | CEDAR ST / S MAIN ST TO JOHN ST / N MAIN ST; SALEM STREET TO CEDAR STREET IN ROCKFORD | Pavement Improvement | $1,443,568 |
ILLINOIS | W OF ILL 26 TO E OF ILL 26 & S OF FAIRVIEW RD TO N US 20B IN FREEPORT | Safety/Traffic Management | $744,460 | |
ILLINOIS | PAVEMENT MARKING IN DISTRICT 1 (INTERSTATE ROUTES) | Safety/Traffic Management | $868,439 | |
ILLINOIS | VARIOUS | Safety/Traffic Management | $600,000 | |
ILLINOIS | PAVEMENT MARKING IN DISTRICT 4 | Safety/Traffic Management | $539,506 | |
ILLINOIS | PAVEMENT MARKING IN DISTRICT 7 | Safety/Traffic Management | $353,667 | |
ILLINOIS | PAVEMENT MARKING IN DISTRICT 9 | Safety/Traffic Management | $477,700 | |
ILLINOIS | GUARDRAIL END SECTION REPLACEMENTS IN DISTRICT 1 | Safety/Traffic Management | $817,871 | |
ILLINOIS | GUARDRAIL END SECTION REPLACEMENTS IN DISTRICT 4 & PEORIA MPO | Safety/Traffic Management | $731,656 | |
ILLINOIS | GUARDRAIL END SECTION REPLACEMENTS IN DISTRICT 9 | Safety/Traffic Management | $684,183 | |
ILLINOIS | GIBSON ST TO SINGER AVE IN NOKOMIS INCLUDING SPRUCE; MADISON ST TO ILL 16 | Pavement Improvement | $943,915 | |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | 26TH ST TO 31ST ST | Pavement Improvement | $317,814 |
ILLINOIS | VARIOUS | Safety/Traffic Management | $1,000,000 | |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | VARIOUS LOCATIONS IN SOUTH COOK COUNTY | Pavement Improvement | $854,514 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | VARIOUS LOCATIONS IN CENTRAL COOK COUNTY | Pavement Improvement | $1,805,948 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | VARIOUS LOCATIONS IN NORTH COOK COUNTY | Pavement Improvement | $1,071,800 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | VARIOUS LOCATIONS IN WILL COUNTY | Pavement Improvement | $500,310 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | VARIOUS LOCATIONS IN KANE COUNTY | Pavement Improvement | $1,595,801 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | VARIOUS LOCATIONS IN DUPAGE COUNTY | Pavement Improvement | $2,555,070 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | VARIOUS LOCATIONS IN MCHENRY COUNTY | Pavement Improvement | $693,261 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | VARIOUS LOCATIONS IN WEST LAKE COUNTY | Pavement Improvement | $2,695,773 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | VARIOUS LOCATIONS IN EAST LAKE COUNTY | Pavement Improvement | $1,500,000 |
ILLINOIS | ST. LOUIS (MO)-IL | UNDER ILL 162 | Pavement Improvement | $29,000,000 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | HUBBARDS CAVE TO I-290 (EISENHOWER EXPY) (RAMP EXTENSION & REMOVAL) | Pavement Improvement | $9,163,712 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | US 41 (SKOKIE BLVD) TO MCCORMICK BLVD; CHICAGO AVE TO JUDSON AVE | Pavement Improvement | $1,664,820 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | NORTHWEST HWY TO N CENTRAL AVE | Pavement Improvement | $2,221,718 |
ILLINOIS | US67 Jackson St in Macomb to S of Troublesome Creek US 136 US67 to .5 Mile E of US 67 | Pavement Improvement | $1,600,000 | |
ILLINOIS | N of Ellison Creek to S of TR 163 | Pavement Improvement | $415,000 | |
ILLINOIS | ILL 116 (W) TO NCL OF CANTON | Pavement Improvement | $2,080,718 | |
ILLINOIS | 1 MI S OF I-74 TO ILL 8 (E) | Pavement Improvement | $1,073,761 | |
ILLINOIS | SCL OF CANTON IL ILL 100; IL 100 TO US 24 | Pavement Improvement | $1,679,288 | |
ILLINOIS | 9.7 miles of resurfacing on IL 78 from north of IL 17 (W) to the Peoria County Line in Stark County. | Pavement Improvement | $2,900,000 | |
ILLINOIS | Bridge replacement of the structure over Sand Ridge Road over Lost Creek south of Ferrin Section 03-10115-00-BR | Bridge Replacement | $50,000 | |
ILLINOIS | Resurfacing FAS 32/FAU 5011 (Poplar Grove Rd) from the Village of Poplar Grove to Marengo Rd in Boone County - 5.28 miles. | Pavement Improvement | $398,954 | |
ILLINOIS | E OF REDDICK RUN TO E OF HERSCHER RD | Pavement Improvement | $1,737,097 | |
ILLINOIS | MEADOWLARK DR TO 1ST ST IN SPRINGFIELD | Pavement Improvement | $818,311 | |
ILLINOIS | LOST CREEK TRIB 3.6, 0.9, 2 MI E OF BLUFF SPRING RD | Pavement Improvement | $2,094,836 | |
ILLINOIS | N OF THAWVILLE TO I-57 AT ONARGA | Pavement Improvement | $861,786 | |
ILLINOIS | DEWITT CO LINE TO 1.5 MI NE OF ILL 121 | Pavement Improvement | $1,465,825 | |
ILLINOIS | Resurface FAS 77 (CH 4) from IL 64 to IL 40 & FAS 79 (CH 25) from IL40 to the Ogle County Line, 10.33 miles in Carroll Co. | Pavement Improvement | $309,728 | |
ILLINOIS | Bridge repalcement - County Highway 6 over Fitch Creek north east of Victoria, Section 05-00096-01-BR | Bridge Replacement | $255,000 | |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | Construct prefabricated pedestrian bridge over Buffalo Creek & construct shared use path between Dundee Road & Glendale Rd * | Transportation Enhancements | $368,060 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | Sidewalk improvement, brick paver sidewalk, pedestrian lighting & signing along FAP 347 (Roosevelt Rd) from Mannheim Road to * | Transportation Enhancements | $268,960 |
ILLINOIS | Construction of the Route 66 multi-use trail in Chenoa Section 06-00025-01-BT | Transportation Enhancements | $25,000 | |
ILLINOIS | ILL 146 TO 3.5 MI N | Pavement Improvement | $992,628 | |
ILLINOIS | Replace existing deck with PCC deck beams, abutment & pier repairs to the structure carrying CH R-15 (Spoon River Rd) over the ** | Bridge Improvement | $379,741 | |
ILLINOIS | Bridge replacement of the structure carrying Morris Rd. over Pulaski Slough south of Pulaski. Section 94-01166-00-BR | Bridge Replacement | $157,081 | |
ILLINOIS | Resurface Old Jacksonville Road from Koke Mill Road 5 miles west to a tributary to Spring Creek in Sangamon County. | Pavement Improvement | $1,775,000 | |
ILLINOIS | ILL 251 (S JCT) TO I-39 | Pavement Improvement | $681,740 | |
ILLINOIS | Bridge replacement over a branch of Indian Creek Section 05-00213-00-BR | Bridge Replacement | $314,054 | |
ILLINOIS | Bridge replacement for the structure carrying CH 23 over Jack Creek, 4 miles northeast of Toulon in Stark County. | Bridge Replacement | $184,642 | |
ILLINOIS | Resurface FAS 188 (CH 8) from the Marshall County Line to FAS 247 in Bureau County - 1.99 miles. | Pavement Improvement | $292,800 | |
ILLINOIS | Resurfacing Freeport Rd. in Ogle County Section 09-00264-00-RS | Pavement Improvement | $574,019 | |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | W OF M L KING DR TO US 6 (159TH ST) | Other | $2,750,000 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | THORNDALE AVE (ELGIN-O'HARE EXPY) TO GRAND AVE & I-88 (E-W TOLLWAY) TO I-90/94 (KENNEDY EXPY) | Other | $5,100,000 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | AT VARIOUS STRUCTURES (103RD, 111TH, 112TH, 115TH, 125TH, 167TH AND AT PEOTONE-JOLIET RD) | Other | $1,300,000 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | HUBBARDS CAVE TO I-290 & FRANKLIN CONNECTOR | Other | $1,189,458 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | AT SAYRE & CENTRAL AVE | Other | $702,536 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | WILL-COOK RD TO W OF US 45; I-355 TO WILL-COOK RD | Other | $1,100,000 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | OVER STATE ST, RRS & LITTLE CALUMET RIVER | Other | $605,580 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | DES PLAINES RIVER, RR CANAL (N ABUTMENT) | Other | $1,000,000 |
ILLINOIS | LOCAL ROADS CONSULTANT | Other | $4,000,000 | |
ILLINOIS | CONSTRUCTION ENGINEERING | Other | $400,000 | |
ILLINOIS | CONSTRUCTION ENGINEERING | Other | $300,000 | |
ILLINOIS | CONSTRUCTION ENGINEERING | Other | $300,000 | |
ILLINOIS | ON-CALL CONSTRUCTION INSPECTION | Other | $1,700,000 | |
ILLINOIS | ON-CALL ENGINEERING | Other | $500,000 | |
ILLINOIS | ST. LOUIS (MO)-IL | UNDER ILL 162 | Other | $2,500,000 |
ILLINOIS | CONSTRUCTION ENGINEERING | Other | $500,000 | |
ILLINOIS | CONSTRUCTION ENGINEERING | Other | $500,000 | |
ILLINOIS | CONSTRUCTION ENGINEERING | Other | $500,000 | |
ILLINOIS | CONSTRUCTION ENGINEERING | Other | $500,000 | |
ILLINOIS | MISCELLANEOUS CONTRUCTION ENGINEERING | Other | $300,000 | |
ILLINOIS | CONSTRUCTION ENGINEERING | Other | $300,000 | |
ILLINOIS | PAVEMENT PROFILE TESTING FOR ECONOMIC RECOVERY PROJECTS | Other | $300,000 | |
ILLINOIS | PEORIA | MISCELLANEOUS CONSTRUCTION ENGINEERING IN DISTRICT 4 | Other | $1,600,000 |
ILLINOIS | 9.50 miles of bituminous surface treatment and seal coat on FAS 242 (CH 16) from the Henry Co. Line to IL 40 in Bureau County. | Pavement Improvement | $128,800 | |
ILLINOIS | 7.85 miles of bituminous treatment and seal coat on FAS 244 (CH 9) from Ch 8 to IL 26 in Bureau Co. | Pavement Improvement | $83,792 | |
ILLINOIS | Resurface FAS 281 (CH 19) Joliet Rd from Lisbon Road to IL 47 in Kendall County - 2.54 miles. | Pavement Improvement | $361,760 | |
ILLINOIS | SW OF TOWANDA TO N OF LEXINGTON | Pavement Improvement | $2,905,931 | |
ILLINOIS | ILL 47 TO ILL 53 | Pavement Improvement | $2,107,029 | |
ILLINOIS | JODAVIESS CO LINE TO REES RD | Pavement Improvement | $1,733,973 | |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | US 12 (MAIN ST) TO LAKE CO LINE | Pavement Improvement | $1,953,958 |
ILLINOIS | ROCKFORD | WHITMAN ST TO WALNUT ST IN ROCKFORD NORTHBOUND AND SOUTHBOUND | Pavement Improvement | $610,289 |
ILLINOIS | ROCKFORD | WINDSOR RD TO N OF ROOSEVELT RD IN LOVES PARK | Pavement Improvement | $1,138,543 |
ILLINOIS | VINE ST IN GRAFTON TO LOCKHAVEN RD | Pavement Improvement | $2,683,927 | |
ILLINOIS | ST. LOUIS (MO)-IL | LOCKHAVEN RD TO STATE ST | Pavement Improvement | $2,090,483 |
ILLINOIS | BUNKER HILL RD TO PARK LANE DR | Pavement Improvement | $684,447 | |
ILLINOIS | 16TH ST TO S OF I-280 IN ROCK ISLAND | Pavement Improvement | $4,449,013 | |
ILLINOIS | ST. LOUIS (MO)-IL | HUMBERT RD | New Bridge Construction | $7,590,000 |
ILLINOIS | 0.1 MI N OF ILL 101 TO 0.2 MI N OF US 24 & 0.2 MI S OF US 24 TO 2 MI SE OF US 24 S OF RUSHVILLE | Pavement Improvement | $3,659,256 | |
ILLINOIS | DAVENPORT-ROCK ISLAND-MOLINE (IA) | N OF 10TH AVE IN MILAN TO 0.1 MI N OF ILL 94 | Pavement Improvement | $3,636,748 |
ILLINOIS | 0.1 MI S OF ILL 125 IN BEARDSTOWN TO MORGAN CO LINE | Pavement Improvement | $2,477,887 | |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | E OF I-355 (VETERAN'S TOLLWAY) TO WARWICK AVE | Pavement Improvement | $2,535,235 |
ILLINOIS | Resurfacing on US 136 (Jackson Street) from west of Ward Street to west of Johnson Street in Macomb in McDonough County. | Pavement Improvement | $350,000 | |
ILLINOIS | N OF ELKHORN ST TO SCL OF POLO | Pavement Improvement | $388,076 | |
ILLINOIS | W OF MCLEAN ST IN GRIDLEY TO W OF I-55 | Pavement Improvement | $1,688,139 | |
ILLINOIS | MOULTRIE CO LINE TO WASHINGTON ST IN TUSCOLA | Pavement Improvement | $2,570,726 | |
ILLINOIS | 0.2 MI S OF ILL 113 TO 0.4 MI N OF I-55 | Pavement Improvement | $2,270,771 | |
ILLINOIS | S OF I-55 TO 0.2 MI S OF ILL 116 | Pavement Improvement | $3,938,465 | |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | US 30/ILL 56 TO S OF PRAIRIE ST; (WB) RAMP TO ILL 47; PRAIRIE ST TO JERICHO RD; JERICHO RD TO KENDALL CO LINE | Pavement Improvement | $2,153,935 |
ILLINOIS | 0.1 MI E OF BRUBAKER CREEK TRIB TO METCALF RD | Pavement Improvement | $756,845 | |
ILLINOIS | E OF LOWE RD E OF KANKAKEE TO W OF ILL 1 (S) | Bridge Improvement | $248,217 | |
ILLINOIS | ROCK CREEK (S BRANCH OF FORKED CREEK) | Bridge Improvement | $237,759 | |
ILLINOIS | IL 17 - Bitiminous concrete resurfacing & aggregate wedges from east of Lowe Rd to west of IL 1 & IL17 intersection in Kankakee Co | Pavement Improvement | $2,897,008 | |
ILLINOIS | GALT RD TO 0.1 MI E OF PROPHET RD W OF ROCK FALLS | Pavement Improvement | $884,511 | |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | WALNUT AVE TO PROSPECT AVE | Pavement Improvement | $811,241 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | LEE/MONHEIN | Pavement Improvement | $989,731 |
ILLINOIS | LOVERS LN NEAR WCL OF HARRISBURG TO ECL | New Construction | $14,121,445 | |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | TRIM CREEK | Pavement Improvement | $540,685 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | WISCONSIN STATE LINE TO ILL 173 (KENOSHA ST) | Pavement Improvement | $523,886 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | ILL 31 TO FOX RIVER | Pavement Improvement | $1,313,266 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | E OF ILL 21 (MILWAUKEE AVE) TO W OF I-94 (TRI-STATE TOLLWAY) | Pavement Improvement | $1,145,733 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | AT BNSF & UP RR 1.3 MI N OF ILL 38 & AT ILL 38 & KRESS CREEK 0.7 MI S OF ILL 38 & AT ABANDONED RR 0.6 MI S OF ILL 64 | Bridge Improvement | $912,972 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | AT US 30 (JOLIET ST) | Pavement Improvement | $7,903,048 |
ILLINOIS | Replace 2 structures carrying FAS 340 (CH 26) over unnamed streams located 5 miles southwest of Paxton in Ford County. | Bridge Replacement | $319,891 | |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | LEE ST TO DES PLAINES RIVER | Pavement Improvement | $1,435,199 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | OVER I-90 (NORTHWEST TOLLWAY) | Bridge Improvement | $670,892 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | ALMOND LN TO W OF MEACHAM RD & HIGGINS ROAD | Pavement Improvement | $1,700,000 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | KRESS CREEK | Bridge Improvement | $397,956 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | STONEY CREEK | Bridge Improvement | $645,881 |
ILLINOIS | AT RIVER ST | Bridge Improvement | $476,279 | |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | ILL 47 TO ORCHARD RD & BLACKBERRY CREEK | Pavement Improvement | $1,064,533 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | DEVON AVE TO ILL 19 (IRVING PARK RD) | Pavement Improvement | $1,648,211 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | FOSTER ST TO TOUHY AVE | Pavement Improvement | $2,513,174 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | CENTRAL AVE TO OLD ORCHARD RD | Pavement Improvement | $650,391 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | 34TH ST TO 46TH ST & AT I-55 (STEVENSON EXPY) | Pavement Improvement | $1,750,000 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | I-294 (TRI-STATE TOLLWAY) TO ILL 1 (HALSTED ST) | Pavement Improvement | $17,864,123 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | I-355 (VETERANS MEMORIAL TOLLWAY) TO WILL-COOK RD | Pavement Improvement | $1,650,012 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | WILL-COOK RD TO W OF US 45 | Pavement Improvement | $1,260,167 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | DES PLAINES RIVER | Bridge Improvement | $606,126 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | M L KING DR/22ND ST TO 0.3 MI W OF US 41 | Pavement Improvement | $3,037,064 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | 0.05m of bridge deck and superstructure rehab of US 30 at IL 394 in the Village of Ford Heights in Cook County. | Bridge Improvement | $2,835,000 |
ILLINOIS | Regrading existing roadway and the replacement of drainage structures on CH 1 Section 86-00075-00-AS | Pavement Improvement | $466,776 | |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | ILL 72 (HIGGINS RD) TO I-90 (NORTHWEST TOLLWAY) | Pavement Improvement | $2,000,000 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | 87TH ST TO 99TH ST | Pavement Improvement | $1,374,077 |
ILLINOIS | CHICAGO-NORTHWESTERN INDIANA (IN) | 87TH ST TO 91ST ST | Bridge Improvement | $500,000 |
Source: FDIC