<< efficiency << | Table Of Contents | >> effortdone >> |
Keyword | effort |
Purpose | Specifies the effort needed to complete the task. An effort of WARNING: In almost all real world projects effort is not the product of time and resources. This is only true if the task can be partitioned without adding any overhead. For more information about this read The Mythical Man-Month by Frederick P. Brooks, Jr. Tasks may not have subtasks if this attribute is used. Setting this attribute will reset the duration and length attributes. A task with an effort value cannot be a milestone. |
|
Syntax | effort <value> (min | h | d | w | m | y) |
|
Arguments | value | A floating point or integer number |
min | minutes |
|
h | hours |
|
d | days |
|
w | weeks |
|
m | months |
|
y | years |
|
Context | task, supplement (task) | |
See also | duration, length |
project "Duration Example" 2007-06-06 - 2007-06-26 { timezone "America/Denver" } resource tux "Tux" task t "Enclosing" { start 2007-06-06 task durationTask "Duration Task" { # This task is 10 calendar days long. duration 10d } task intervalTask "Interval Task" { # This task is similar to the durationTask. Instead of a start # date and a duration it has a fixed start and end date. end 2007-06-17 } task lengthTask "Length Task" { # This task 10 working days long. So about 12 calendar days. length 10d } task effortTask "Effort Task" { # Tux will need 10 days to complete this task. effort 10d allocate tux } }
<< efficiency << | Table Of Contents | >> effortdone >> |