The TaskJuggler III User Manual

Project Management beyond Gantt Chart Drawing


<< interval2 << Table Of Contents >> interval4 >>


Keyword interval3

Purpose

There are three ways to specify a date interval. The first is the most obvious. A date interval consists of a start and end DATE. Watch out for end dates without a time specification! Date specifications are 0 extended. An end date without a time is expanded to midnight that day. So the day of the end date is not included in the interval! The start and end dates must be separated by a hyphen character.

In the second form, the end date is omitted. A 24 hour interval is assumed.

The third form specifies the start date and an interval duration. The duration must be prefixed by a plus character.

Syntax <date> [(- <date> | + <duration> (min | h | d | w | m | y))]
Arguments date
See date for details.
duration
The duration of the interval. May not be 0.
min
minutes
h
hours
d
days
w
weeks
m
months
y
years
Context Global scope



<< interval2 << Table Of Contents >> interval4 >>