The TaskJuggler User Manual

Project Management beyond Gantt Chart Drawing


<< timezone (export) << Table Of Contents >> timezone (shift) >>


Keyword timezone (report)

Purpose
Sets the time zone used for all dates in the report. This setting is ignored if the report is embedded into another report. Embedded in this context means the report is part of another generated report. It does not mean that the report definition is a sub report of another report definition.
Syntax timezone <STRING>
Arguments none
Context accountreport, resourcereport, taskreport, textreport, tracereport



<< timezone (export) << Table Of Contents >> timezone (shift) >>


Copyright (c) 2006, 2007, 2008, 2009, 2010, 2011, 2012, 2013 by Chris Schlaeger <chris@linux.com>.TaskJuggler is a trademark of Chris Schlaeger.