The TaskJuggler User Manual

Project Management beyond Gantt Chart Drawing


<< work << Table Of Contents >> workinghours (resource) >>


Keyword workinghours (project)

Purpose

Set the default working hours for all subsequent resource definitions. The standard working hours are 9:00am - 12:00am, 1:00pm - 18:00pm, Monday to Friday. The working hours specification limits the availability of resources to certain time slots of week days.

These default working hours can be replaced with other working hours for individual resources.

Syntax workinghours <weekday> [- <end weekday>] [, <weekday> [- <end weekday>]...] (off | <TIME> - <TIME> [, <TIME> - <TIME>...])
Arguments weekday
Weekday (sun - sat)
end weekday
Weekday (sun - sat). It is included in the interval.
Context project
See also dailyworkinghours, workinghours (resource), workinghours (shift)

project prj "Example Project" "1.0" 2007-01-01 - 2007-03-09 {
  # The following attributes are all optional. They illustrate the
  # default values. These attributes are only needed if you want to
  # specify different values than those listed below.
  timingresolution 60min
  timezone "America/Denver"
  dailyworkinghours 8
  yearlyworkingdays 260.714
  timeformat "%Y-%m-%d %H:%M"
  shorttimeformat "%H:%M"
  currencyformat "(" ")" "," "." 0
  weekstartsmonday
  workinghours mon - fri 9:00 - 12:00, 13:00 - 18:00
  workinghours sat, sun off
  scenario plan "Plan" {
  }
}

task t "Task" {
  start 2007-01-01
}


<< work << Table Of Contents >> workinghours (resource) >>


Copyright (c) 2006, 2007, 2008, 2009, 2010, 2011, 2012 by Chris Schlaeger <chris@linux.com>.TaskJuggler is a trademark of Chris Schlaeger.