The TaskJuggler User Manual

Project Management beyond Gantt Chart Drawing


<< priority << Table Of Contents >> project >>


Keyword priority (timesheet)

Purpose
The priority is a value between 1 and 1000. It is used to determine the sequence of task when converting work to bookings. Tasks that need to finish earlier in the period should have a high priority, tasks that end later in the period should have a low priority. For tasks that don't get finished in the reported period the priority should be set to 1.
Syntax priority <INTEGER>
Arguments none
Context newtask, task (timesheet)