project "Leaves" 2012-03-12 +6m { scenario s1 "S1" { scenario s2 "S2" } } vacation "Goof-out day" 2012-03-14 resource r1 "R1" { vacation 2012-03-19 +1w } task "T1" { effort 20d allocate r1 fail s1.end != 2012-04-16-17:00 fail s2.end != 2012-04-16-17:00 } taskreport "Leaves" { formats html columns no, name, start, end, daily scenarios s1, s2 hideresource 0 }